Lesson 6 of 8 · about 15 minutes
The Cassia County Data Center Proposal
You'll be able to
- State what TerraVolt's SEC filings say about the Idaho campus, its land and its schedule
- Separate what is confirmed in primary records from what rests on secondary sources, including the Cassia County location
- Convert a daily gas contract volume into an approximate power plant size
- List the local and state approvals a behind-the-meter gas data center would need
The Cassia County data center is the most talked-about project in this course with the least public paper behind it. Thin paper calls for knowing exactly which facts come from where, because a project like this can move from rumor to rezoning hearing in a few months.
Who is behind it
The developer is TerraVolt Infrastructure, Inc., a subsidiary of a small public company that was called CalEthos, Inc. and now files with the SEC as TerraVolt Holdings, Inc. Because it is public, it has to report its plans and its money every quarter. Those filings are the best primary source available.
Its fiscal 2025 annual report (Form 10-K) says the company abandoned an earlier site in Imperial County, California and moved to a "business-friendly Northwestern U.S. location": flat, buildable agricultural land outside the 100-year and 500-year flood zones. Trade press in May 2026 placed the campus in southeast Idaho on the Northwest natural gas pipeline. The More Than Just Parks data center tracker names it the "Cassia County Data Center Campus" and lists it as proposed at 240 MW. BoiseDev reported in April 2026 that the campus was proposed in the Raft River area between Twin Falls and Pocatello, and that the governor's office referred questions to Cassia County's economic development agency. Neither SEC filing reviewed for this lesson names Cassia County, and this course found no Cassia County agenda item on it. Treat the county as likely but unconfirmed until a county record shows up.
What the filings say
| Item | What the record shows | Source |
|---|---|---|
| Power plan | A behind-the-meter gas plant on site; initial campus phase of 200 to 240 MW | 10-Q (plant); DCD, May 12, 2026 (MW) |
| Gas contract | 55,000 MMBtu a day from an unnamed marketer, signed April 2026; reservation fee of $3,832,500 paid in May 2026 | 10-Q |
| Growth plan | Gas sized for an initial 300 to 350 MW; a planned 2030 pipeline expansion for another 300 to 600 MW | 10-K |
| Delivery dates | Start-date notice by April 30, 2028; start date no later than July 31, 2029; each extendable up to eight months | 10-Q |
| Collateral | $6 million standby letter of credit delivered August 2026 (expires March 31, 2029), backed by a cash deposit; a delivery-period letter of credit of up to $50 million required before deliveries begin | 10-Q |
| Land | Not secured as of June 30, 2026; negotiating with several landowners, expecting site control within 60 days | 10-Q |
| Approvals | Land-use applications and zone changes with the county planning department, with approvals expected by year-end 2026 (10-K); environmental reports before end of 2026; all construction approvals targeted for the second quarter of 2027 (10-Q) | 10-K; 10-Q |
| Money | $15 million advanced in April 2026 by a related-party trust; a $16 million 8 percent note due April 30, 2028; cash of $10,689,000 at June 30, 2026; total liabilities of $16,623,000 | 10-Q |
| Viability | No recurring revenue; accumulated deficit about $40.6 million; management states substantial doubt about continuing as a going concern; says it needs "substantial additional financing" | 10-Q |
Read that table twice. The company has a firm gas contract and real money at risk on it. It also has no land, no revenue and a going concern warning. Both are true. A project in this condition can still file a rezone, and a county can still approve one, so the financial picture belongs in the hearing record.
Example: how big a power plant does 55,000 MMBtu a day fuel?
A heat rate says how much fuel a plant burns per kWh. Use two assumed round numbers: 9,000 Btu/kWh for engines or simple-cycle turbines, and 6,500 Btu/kWh for an efficient combined-cycle plant.
- Daily fuel: 55,000 MMBtu x 1,000,000 = 55,000,000,000 Btu.
- At 9,000 Btu/kWh: 55,000,000,000 / 9,000 = 6,111,111 kWh a day = 6,111 MWh. Divided by 24 hours = about 255 MW running nonstop.
- At 6,500 Btu/kWh: 55,000,000,000 / 6,500 = 8,461,538 kWh = 8,462 MWh a day. Divided by 24 = about 353 MW.
So the contract supports a plant of roughly 250 to 350 MW running all day, which lines up with the 10-K's "initial 300 Megawatt (MW) to 350MW" and the 200 to 240 MW first phase after allowing for losses, cooling and backup. A gas plant that size is a major air emissions source, which brings in the state air permit discussed below.
What it still needs
A behind-the-meter gas data center skips some steps that a grid-served one takes, but not the local ones.
- Land and zoning. Site control, then a zone change or conditional use permit under the county code and Idaho's Local Land Use Planning Act. The company told investors it expects conversion to light industrial zoning in under 12 months.
- Air permit. A gas plant of a few hundred megawatts needs a permit to construct from the Idaho Department of Environmental Quality before building. The 10-K said design and environmental documents for the plant would go to state agencies by mid-2026.
- Water. Cooling a 200 MW campus takes water unless it uses air or closed-loop systems. House Bill 895, signed April 2, 2026, added Idaho Code 42-252 on data center cooling water. Any new use also runs into Idaho's water rights system, where new appropriations can be denied in areas that are fully claimed, under a moratorium, or designated critical or ground water management areas.
- Utility. Behind-the-meter does not always mean off-grid. If the campus wants backup or exchange service from the local utility, that contract would go to the PUC or, for a cooperative or municipal utility, to its board. For a PUC-regulated utility, a contract adding 50 MW or more signed on or after July 1, 2026 falls under Idaho Code 61-335, which requires commission approval and full cost of service.
- Roads, fire and emergency service. The county will need agreements for road impacts and for fire protection at a site with gas lines, turbines or engines, and large battery or diesel backup.
The arguments
The case for, as the company makes it: a self-powered campus that does not lean on the Idaho Power system, on flat farm ground near an existing pipeline, bringing construction work, capital investment and a new tax base to a rural county.
The case against, as made by data center critics and in Jeff Pierson's Feeding the Beast series: a large gas plant's air emissions in an agricultural valley, water use, conversion of farmland, few permanent jobs relative to the investment, and the risk of a half-built project from a developer that reports substantial doubt about its own survival. Pierson's broader point, that projects land where the fence is lowest, applies directly: a county without a data center ordinance is deciding under rules written for warehouses.
Where the evidence points: the financial risk is documented by the company itself. The environmental and land effects can't be judged until a site and a design are on file.
Common mix-ups
- Claim: The Cassia County data center has been approved. What the evidence shows: As of June 30, 2026 the developer had not secured land, and it targets construction approvals in the second quarter of 2027.
- Claim: It will raise Idaho Power rates. What the evidence shows: The plan is a behind-the-meter gas plant. Grid cost effects depend on whether it later seeks utility service, which is not in the filings.
- Claim: A gas contract means the project is certain. What the evidence shows: The contract has deadlines and extensions through 2029 and requires a letter of credit of up to $50 million before deliveries. The company says it needs substantial additional financing.
Reporting angle
- Ask the Cassia County Zoning and Building office whether TerraVolt or any affiliate has filed a pre-application, zone change or conditional use permit. Request the file under Idaho Code 74-102.
- Check Idaho DEQ's air permit application list for a permit to construct tied to TerraVolt or the campus.
- Read each new TerraVolt 10-Q and 8-K on SEC EDGAR for land purchases, county approvals and new financing; the next quarterly report covers September 30, 2026.
- Ask the Idaho Department of Water Resources whether any water right application or transfer names the company or its landowners.
- Ask county commissioners whether they will require a decommissioning bond and financial assurance given the company's going concern statement.
Research angle
- TerraVolt Form 10-Q, June 30, 2026: gas contract, land status, finances and the going concern statement.
- CalEthos Form 10-K, fiscal 2025: the move from California to the Northwest and the approval timeline.
- Data Center Dynamics on the gas deal: trade coverage of the first phase.
- More Than Just Parks tracker entry: the source of the Cassia County label.
- Cassia County website: county code, zoning applications and the meeting archive.
- Zoning questions for a data center: why the use-table label matters.
Check yourself
1. As of June 30, 2026, what did TerraVolt's quarterly SEC filing say about land for the Idaho campus?
The Form 10-Q says the company had not secured land as of June 30, 2026, was negotiating with several landowners, and expected site control within 60 days.
2. TerraVolt's gas supply agreement is for 55,000 MMBtu per day. At an assumed heat rate of 9,000 Btu per kWh, about how large a plant could that fuel running around the clock?
55,000 x 1,000,000 Btu = 55 billion Btu a day. Divided by 9,000 Btu/kWh = about 6.1 million kWh a day, or 6,111 MWh. Divided by 24 hours = about 255 MW.
3. What did management say in the June 30, 2026 filing about the company's ability to keep operating?
The 10-Q reports no recurring revenue, an accumulated deficit of about $40.6 million, and management's statement of substantial doubt about continuing as a going concern.
4. Which source places the TerraVolt campus in Cassia County?
The filings and trade coverage describe southeast Idaho on the Northwest Pipeline. The Cassia County label comes from a third-party tracker, so it needs confirmation from county records.
5. Under the gas agreement, what is the latest the gas delivery start date can be, absent extensions?
The 10-Q says a start-date notice is due by April 30, 2028 and a start date must be designated no later than July 31, 2029, each extendable by up to eight months.
Terms in this lesson
- Behind-the-meter generation
- A power plant that serves a customer directly on site rather than selling into the utility grid first.
- MMBtu
- One million British thermal units, the standard unit for natural gas contracts.
- Heat rate
- The fuel a plant burns per kilowatt-hour it makes, in Btu per kWh; lower is more efficient.
- Going concern doubt
- A statement in financial reports that a company may not have the money to keep operating for the next year.
- Letter of credit
- A bank's promise to pay a seller if the buyer doesn't, often backed by a cash deposit.
Sources
- TerraVolt Holdings (formerly CalEthos) Form 10-Q for the quarter ended June 30, 2026 checked 2026-10
- CalEthos Inc. Form 10-K for fiscal year 2025 checked 2026-10
- Data Center Dynamics, TerraVolt inks natural gas supply deal for onsite power plant at planned data center campus in Idaho (May 12, 2026) checked 2026-10
- Pipeline and Gas Journal, TerraVolt taps Northwest Pipeline for Idaho AI data center project (May 2026) checked 2026-10
- More Than Just Parks, Data Center Tracker: Cassia County Data Center Campus checked 2026-10
- BoiseDev, Legislature leaves big tax breaks for data centers on the books (April 6, 2026) checked 2026-10
- Cassia County, Idaho, official website (zoning, county code, meetings) checked 2026-10
- Idaho Legislature, 2026 House Bill 895 (data center cooling water, Idaho Code 42-252) checked 2026-10