Lesson 1 of 8 · about 16 minutes
The Southern Idaho Build-Out at a Glance
You'll be able to
- Name the major southern Idaho energy and data center projects and their status as of October 2026
- Sort a project by stage, from announced idea to operating plant, and say what each stage means
- Match each kind of project to the body that approves it: a county, the Idaho PUC, the BLM or FERC
- Add up proposed megawatts and compare them to Idaho Power's own forecast of peak growth
Southern Idaho has more energy and data center proposals in motion right now than at any point in its history, and they are all at different stages. Some are signed orders. Some are a line in a securities filing. One is a cancelled federal approval that its developer has never publicly given up on. Treating them as the same kind of thing is the fastest way to lose an argument at a public hearing.
This lesson is the map. The rest of the course takes each piece in turn. Every status below is dated, because these change month to month, and a status that was right in July can be wrong by October.
Stages, from idea to steel
A project's stage tells you who can still change it and how.
Announced projects have no record to comment on. Applied projects have a case number and, usually, a deadline. Projects in review have a hearing or an environmental analysis where evidence goes in. Approved projects can still be appealed for a short window, and they can still fail for money reasons. Paused and cancelled projects belong in their own box, because the reason they stopped decides whether they can start again.
The map, as of October 2026
| Project | What and where | Size | Status (date) | Who decides |
|---|---|---|---|---|
| SWIP-North | 500 kV line, Midpoint Substation near Twin Falls to Robinson Summit near Ely, Nevada | 285 miles; 500 MW northbound for Idaho Power | PUC certificate Dec. 12, 2025 (Order 36874); groundbreaking Sept. 3, 2026; service expected 2028 | BLM (federal land), PUC (Idaho Power's share), counties (private land) |
| Lava Ridge Wind | Magic Valley Energy (LS Power), BLM land in Lincoln, Minidoka and a third Magic Valley county | Up to 231 turbines, about 1,000 MW | Approved Dec. 2024; frozen Jan. 20, 2025; Interior announced reversal Aug. 6, 2025 | BLM and Interior |
| South Hills gas plant | Idaho Power, Twin Falls County | 222 MW | PUC case IPC-E-26-04 open, no final order as of Sept. 25, 2026; target June 1, 2029 | PUC; county for land use |
| Peregrine gas plant | Idaho Power, Elmore County | 430 MW | Same PUC case; county findings on CUP-2025-32 on the April 30, 2026 P&Z agenda; target June 1, 2030 | PUC; Elmore County |
| Taurus Wind and Snake River Energy Solar | Arevia Power, BLM land in Gooding, Lincoln and a neighboring county | 500 MW wind, 400 MW solar, 550 MW storage | BLM scoping forum Jan. 28, 2025; no later decision found | BLM |
| Rhea Data center | Arevia Power subsidiary, BLM land in southern Ada County, rights-of-way into Elmore County | About 3,750 acres; MW not disclosed | BLM pre-planning; notice of intent planned before end of 2026 | BLM; PUC for any power contract |
| TerraVolt campus | Southeast Idaho on a gas pipeline; a third-party tracker places it in Cassia County | 200 to 240 MW first phase | No land secured as of June 30, 2026, per SEC filing | County zoning; state air permit |
| Soles Rest Solar | Western Elmore County, leased private land | Up to 149 MW on about 981 acres | Staff recommended approval; workshop July 23, 2026 | Elmore County; PUC for the power contract |
The table leaves out older and smaller items covered later: Crimson Orchard Solar and storage in Elmore County, the long-suspended Salmon Falls Wind request near Rogerson, Desert Ridge Winds in eastern Elmore County, and data center proposals in Kuna and Pocatello.
Who decides what
Residents reach each of these decision-makers through a different door.
- Counties and cities decide land use on private land through zoning and conditional use permits under Idaho's Local Land Use Planning Act, Idaho Code 67-6501 and following. Hearings are local and comment is open to anyone.
- The Idaho Public Utilities Commission decides whether Idaho Power can build or buy a resource and charge customers for it, and sets terms for big customers. Anyone can file written comments in a case.
- The Bureau of Land Management decides projects on federal land through right-of-way grants and National Environmental Policy Act review. Its decisions follow federal policy, which changes with administrations.
- FERC regulates interstate transmission rates and hydropower licenses, such as pumped storage.
A county cannot set an electric rate. The PUC cannot zone land. The BLM does not answer to a county commission, though federal law requires it to coordinate with local plans. Knowing which door to knock on saves months.
Example: how much of the forecast do the gas plants cover?
Idaho Power's 2025 Integrated Resource Plan, acknowledged by the PUC on February 17, 2026, forecast peak demand rising about 1,700 MW over 20 years, with about 1,000 MW in the first five years.
- Proposed gas plants: South Hills 222 MW + Peregrine 430 MW = 652 MW.
- Share of five-year peak growth: 652 / 1,000 = 0.652, about 65 percent.
- Add SWIP-N's 500 MW of northbound capacity: 652 + 500 = 1,152 MW, more than the five-year growth figure on its own.
That last line does not mean Idaho Power is overbuilding. Capacity ratings are not interchangeable: a transmission entitlement only helps if there is power to buy on the other end at the peak hour, and a gas plant's rating drops on hot days. But the arithmetic gives you a fair question for the PUC: how do the line and the two plants fit together in the utility's own capacity math, and what happens to the gas plant need if SWIP-N is late?
Common mix-ups
- Claim: Lava Ridge is dead, so the transmission line is dead too. What the evidence shows: They are separate projects. SWIP-N got its PUC certificate in December 2025 and broke ground in September 2026.
- Claim: A data center that is in the news has been approved. What the evidence shows: The Cassia County proposal had not secured land as of its June 30, 2026 filing, and the Rhea Data proposal was in BLM pre-planning in September 2026.
- Claim: The county commission decides everything. What the evidence shows: Federal land goes through the BLM, and utility plants go through the PUC. The county decides land use on private land.
Reporting angle
- Keep a dated status log for every project in the table. Write the date you checked next to each status.
- For each project, find the case number: PUC case (IPC-E-26-04), county CUP number (CUP-2025-29, CUP-2025-32), or BLM serial number. No case number means no decision is pending.
- Request county application files under the Idaho Public Records Act, Idaho Code 74-102. Under Idaho Code 74-103, agencies must respond within three working days or say they need more time, up to ten working days.
- Ask Idaho Power how SWIP-N's 500 MW and the two gas plants are counted against the 2029 and 2030 capacity deficits in IPC-E-26-04.
- Watch the Elmore County P&Z calendar; its October 2026 meeting moved to American Legion Post 26 on October 22.
Research angle
- Idaho PUC case IPC-E-26-04: every filing on the South Hills and Peregrine gas plants.
- PUC Order No. 36874: the SWIP-N certificate and what it did and did not decide.
- Federal Register notice of the Lava Ridge Record of Decision: the official description of what was approved.
- Elmore County Land Use and Building Department: agendas, staff reports and pending CUPs.
- BLM National NEPA Register: search federal-land projects by name for documents and comment periods.
- Jeff A. Pierson, The Machine Comes to the Magic Valley (Feeding the Beast No. 5): the case that the land rush follows cheap power and light oversight.
Check yourself
1. Which body decides whether Idaho Power may build the Peregrine and South Hills gas plants as utility investments?
Idaho Power applied on March 11, 2026 for certificates of public convenience and necessity in IPC-E-26-04. The counties handle land use; the PUC decides whether the plants are needed and how costs reach rates.
2. As of October 2026, what is the status of the Lava Ridge Wind Project?
The BLM approved it in December 2024. A January 20, 2025 presidential memorandum froze it, and on August 6, 2025 Interior announced it was reversing the approval.
3. Idaho Power's 2025 IRP forecast about 1,000 MW of new peak demand in the first five years. The two proposed gas plants total 652 MW. What share of that five-year growth do they cover?
222 MW + 430 MW = 652 MW. 652 / 1,000 = 0.652, about 65 percent.
4. A developer has announced a project in a press release but filed nothing with a county, the BLM or the PUC. What stage is it in?
Until an application is filed, no public body has a record or a deadline. Announcements are leads to check, not decisions.
5. Which of these is the main reason the SWIP-N line matters to the rest of this course?
SWIP-N is a 285-mile, 500 kV line. Wind and solar developers in the Magic Valley planned around the transmission it adds, which is why it keeps coming up.
Terms in this lesson
- CPCN
- Certificate of public convenience and necessity: Idaho PUC permission for a utility to build a major plant or line as a utility investment.
- Conditional use permit (CUP)
- A county or city land-use approval for a use allowed in a zone only after a hearing and with conditions.
- Right-of-way grant
- BLM permission to use federal land for a road, line, pipeline or energy facility, issued under 43 U.S.C. 1761.
- Interconnection queue
- The utility's waiting list of generators asking to connect to its grid, with study milestones and a status for each request.
- Nameplate capacity
- The maximum output a plant is rated for, in megawatts, before accounting for weather, fuel or outages.
Sources
- Idaho PUC, Case IPC-E-26-04 summary (South Hills and Peregrine CPCNs), updated Sept. 25, 2026 checked 2026-10
- Idaho PUC news release on IPC-E-26-04 (April 7, 2026) checked 2026-10
- Idaho PUC Final Order No. 36874, Case IPC-E-25-08 (SWIP-North CPCN), Dec. 12, 2025 checked 2026-10
- T&D World, Great Basin Transmission begins construction on SWIP-North (Sept. 2026) checked 2026-10
- U.S. Interior Department, moves to cancel Lava Ridge approval (Aug. 6, 2025) checked 2026-10
- Idaho PUC news release, Idaho Power 2025 IRP acknowledged (Feb. 18, 2026) checked 2026-10
- Elmore County Planning and Zoning agenda, April 30, 2026 checked 2026-10
- BLM, public forum on proposed Taurus Wind and Snake River Energy Solar projects (Jan. 2025) checked 2026-10
- East Idaho News, data center with power plant planned for public land (Sept. 21, 2026) checked 2026-10
- TerraVolt Holdings (formerly CalEthos) Form 10-Q for the quarter ended June 30, 2026 checked 2026-10