Lesson 2 of 9 · about 17 minutes

Zoning Questions: Is a Data Center Even an Allowed Use?

You'll be able to

  • Read a zoning use table and tell permitted, conditional and prohibited uses apart
  • Explain why the choice between warehouse, industrial, utility or a new data center category changes the rules that apply
  • Compute how much of a parcel is buildable after setbacks
  • Name the Idaho notice requirements for rezones and special use permits and why notice defects matter

Before anyone argues about noise or water, somebody has to answer a dull question: does the zoning code allow a data center on this parcel at all? The answer decides whether there is a public hearing, which standards apply and how much say neighbors get. And in a lot of counties written before 2020, the code never mentions data centers.

Reading the use table

Most zoning codes have a use table: uses down the side, zones across the top, and a letter in each cell. The letters vary by code, but the meanings are close to universal.

Use (invented Brindle County code)AGRRC-2M-1M-2
Warehouse and distributionPPP
Light manufacturingCPP
Public utility facilityCCCPP
Data centerNot listed

P means permitted by right: staff approve it if it meets the written standards, no hearing. C means conditional: allowed only after a hearing and with conditions. A blank means prohibited. In Idaho, the state enabling law calls conditional approval a special use permit (Idaho Code 67-6512), though many local codes still say conditional use permit.

Now the hard part. Data center is not listed. The county can handle that gap in several ways, and each one produces a different public process.

PathWhat happensPublic hearing?Who it affects
Similar use determinationThe planning director rules a data center is "like" a warehouse or utility facilityUsually no, but often appealableThis parcel, and every later applicant who cites the ruling
RezoneThe parcel moves to a zone where the chosen category is allowed, often AG to M-1 or M-2YesThis parcel
Special or conditional use permitThe parcel stays in its zone; the use is allowed with conditionsYesThis parcel
Text amendmentA "data center" row is added to the use table, with standardsYesEvery parcel in every zone the new row covers

Why the warehouse label matters

Say Brindle County's planning director decides a data center is a warehouse. Warehouses are permitted by right in C-2, M-1 and M-2. The developer can now build in a commercial zone next to houses with no hearing.

The warehouse standards were written for trucks and storage. They cover loading docks, parking ratios and maybe hours for deliveries. They say nothing about cooling equipment running 24 hours a day, a yard of diesel generators, a fuel farm, or a substation. A data center has fewer trucks than a warehouse after construction and far more mechanical noise. The category fits the building shell and misses everything that makes neighbors call the county.

The utility label has the opposite problem. Some codes allow utility facilities nearly everywhere, because nobody wants to forbid a pump station. Calling a 200 MW campus a utility facility can open agricultural and residential zones.

That is why counties with long experience have written their own categories and standards. Loudoun County, Virginia, at the center of the Northern Virginia data center market, voted on March 18, 2025 to end by-right approval entirely. Each new data center there now needs a special exception, which means hearings before the Planning Commission and the Board of Supervisors. The county's second phase, still underway as of October 2026, is writing use-specific standards for data centers and utility substations. Next door, Fairfax County adopted its amendment on September 10, 2024. Among its terms:

  • Data center buildings at least 200 feet from an adjacent residential lot line, unless a special exception allows less.
  • Generators and similar equipment 300 feet from a residential lot line, or shielded from it by the building.
  • At least one mile from a Metro station, to save land near transit for other uses.
  • Pre- and post-construction noise studies showing compliance with the county noise ordinance.
  • All equipment enclosed or screened by a wall or similar barrier.

Kent County, Delaware went further in July 2026: 300 feet from residentially zoned land for buildings, and 400 feet for generators, cooling towers and chillers (300 feet if housed in a noise-reducing building).

Setbacks eat land fast

Example: what's left after setbacks

The Tamarack site in invented Brindle County includes a square 160-acre parcel. A square mile is 640 acres and 5,280 feet on a side, so a quarter section is 2,640 feet on a side.

  • Setback of 300 feet on all four sides: 2,640 minus (2 x 300) = 2,040 feet per side.
  • Buildable area: 2,040 x 2,040 = 4,161,600 square feet.
  • In acres: 4,161,600 / 43,560 = about 95.5 acres. That is 60 percent of the parcel.

Now suppose homes border only the north side and the county uses Kent County's numbers: 300 feet for buildings everywhere, 400 feet for outdoor equipment on the residential side.

  • Equipment zone loses another 100 feet along the north edge: 100 x 2,040 = 204,000 square feet, about 4.7 acres, where buildings may go but generators may not.
  • A 1,000-foot setback from homes on the north side, which some residents ask for: north-south dimension becomes 2,640 minus 1,000 minus 300 = 1,340 feet. Area = 1,340 x 2,040 = 2,733,600 square feet, about 62.8 acres.

Every setback number at a hearing is also a number of buildings. A developer who says a setback "kills the project" may be right or may be bargaining. Ask for the site plan at each distance.

Height, substations and the things beside the building

Many data center buildings are one or two stories with tall floor heights, and rooftop cooling equipment adds more. Where land is scarce, developers build multi-story data centers. Ask for the height to the top of rooftop equipment, not just the roof deck. In Idaho, height also changes who gets notice: Idaho Code 67-6512 requires mailed notice out to at least three times the allowed height for special use permits on structures over 100 feet, and at least one mile for unincorporated structures 400 feet or taller.

Then there is everything outside the building:

  • Substation. A campus of hundreds of megawatts usually needs its own high-voltage substation. Some codes treat substations as utility uses allowed in many zones. Ask whether the substation is part of this application or will come later through a separate utility approval, and who will own it.
  • Transmission lines. New lines may cross other parcels and need their own permits and easements.
  • Generator yard and fuel storage. Fire code and air permits apply, but zoning decides where on the site they sit.
  • Battery storage. Large lithium-ion installations raise fire-separation questions the zoning code may not address.

Notice: the boring step that can void everything

Idaho's notice rules for land-use decisions are specific. For a rezone, Idaho Code 67-6511 requires mailed notice to owners within 300 feet, posting on the site at least a week before the hearing, and, when 200 or more owners are involved and the county has no alternative procedure, a display ad at least 4 inches by 2 columns in the official newspaper at least 15 days ahead. Special use permits under 67-6512 need published notice at least 15 days before the hearing, the same 300-foot mailing and posting a week ahead.

Skipping a step is not a technicality. In Virginia, the Prince William County Board of Supervisors rezoned about 1,790 acres for the Prince William Digital Gateway in December 2023, after a 29-hour hearing. The project would have covered about 2,100 acres next to Manassas National Battlefield Park with about 23 million square feet of data centers. In August 2025 a circuit judge voided the rezoning: a required newspaper ad never ran, later ads did not meet the legal timing, and the documents were not available for public review in time. The Virginia Court of Appeals upheld that ruling in late March 2026. The county withdrew its defense on April 14, co-developer Compass declined further appeals, and QTS dropped its appeal to the Supreme Court of Virginia on July 2, 2026. One of the largest data center projects ever proposed in the United States died over a newspaper schedule.

Common mix-ups

  • Claim: If the code doesn't mention data centers, they aren't allowed. What the evidence shows: Often staff fit them into an existing category. Ask whether a similar use determination has been made and whether it can be appealed.
  • Claim: A text amendment is just paperwork for one project. What the evidence shows: It changes the rules for every parcel in the affected zones, including ones nobody at the hearing is thinking about.
  • Claim: Rezoning to industrial is a small step because the parcel is near other industry. What the evidence shows: Under Idaho Code 67-6511 the change must not conflict with the comprehensive plan, and the board must weigh effects on public services such as schools.

Reporting angle

  • Pull the county use table and find every category a data center could fall under. Ask planning staff which one they are using and whether that choice was written down.
  • Ask for the site plan with setbacks marked, plus the height to the top of rooftop equipment.
  • Check the notice: date of the newspaper ad, date of posting, the mailing list and its radius. Compare each to the statute.
  • Ask whether the substation and any new transmission line are in this application.
  • If a text amendment is proposed, map every parcel it would cover, and publish the map.

Research angle

Check yourself

1. In March 2025, what did the Loudoun County, Virginia Board of Supervisors change about data centers?

2. Fairfax County's September 2024 data center amendment set what minimum distance between a data center building and an adjacent residential lot line, absent a special exception?

3. A square 160-acre parcel (2,640 feet on a side) must keep buildings 300 feet from every boundary. About how many acres remain buildable?

4. Why did a Virginia court void the 2023 rezoning for the Prince William Digital Gateway?

5. Under Idaho Code 67-6512, a special use permit for a structure taller than 100 feet requires mailed notice to owners within what distance?

6. A planning director rules that a data center counts as a warehouse under an older code. What is the main risk?

Terms in this lesson

Use table
The chart in a zoning code that lists each use and marks whether it is permitted, conditional or prohibited in each zone.
By-right use
A use the zone permits outright, approved administratively if it meets the written standards, with no public hearing.
Text amendment
A change to the wording of the zoning code itself, such as adding a data center category, that applies to every parcel in the affected zones.
Setback
The minimum distance a building or piece of equipment must keep from a property line, road or neighboring zone.
Similar use determination
A staff ruling that an unlisted use should be treated like a listed one; usually appealable.