Lesson 5 of 9 · about 18 minutes
Water Planning: City Contracts, Water Rights and Reclaimed Supply
You'll be able to
- Compare city supply contracts, new groundwater rights, transfers of existing rights and reclaimed water
- Describe the IDWR notice, protest and review criteria for new applications and transfers
- Convert gallons per day into acre-feet per year and cubic feet per second
- List the terms that belong in a data center water service agreement
A data center's water use usually gets described as a number: so many gallons a day. The planning question is where those gallons come from, who has the legal right to them, and what happens on the hottest week of a dry year. In Idaho, that means water rights under the prior appropriation doctrine, the Idaho Department of Water Resources (IDWR), and the city utility if there is one.
How much water a given cooling design uses is covered in the water lesson of the impacts module. This lesson is about supply.
Where the water can come from
| Path | Who decides | Public process | Main risks |
|---|---|---|---|
| City or water district supply contract | City council or district board; the provider must already hold enough water rights | Council vote; sometimes bundled with annexation | Peak-day capacity, priority in shortages, who pays for new wells and pipes |
| New groundwater right | IDWR | Published notice, 10-day protest period, hearing if protested | Moratorium areas, injury to senior rights, aquifer decline |
| Transfer of an existing right | IDWR | Same notice and protest as a new application | Taking water out of farming; injury and enlargement tests |
| Reclaimed (recycled) water | City wastewater utility, with state environmental permits | Council vote; DEQ permit | Pipeline not built yet, seasonal limits, existing commitments to reuse |
City supply
Most data centers that want city water also want city sewer, which is a big reason projects ask to be annexed. Idaho Code 42-202B defines municipal purposes to include industrial use, when a municipal provider supplies it to users in its service area. It also lets providers hold water rights for "reasonably anticipated future needs," but those needs must fit the land use plans the municipality has approved. So a city's land-use plan, its annexation decisions and its water rights all connect. A city that says it has "plenty of water rights" should be asked: how much is in hand and pumpable today, and how much is a paper right for future growth?
The key city document is the will-serve letter, followed by a water service agreement. Ask for both.
New groundwater rights
A data center on its own wells needs a permit from IDWR, unless it qualifies for a small domestic exemption, which a data center will not. Under Idaho Code 42-203A, notice runs once a week for two weeks in a local newspaper (statewide circulation for diversions over 10 cfs or 1,000 acre-feet) and on IDWR's website. Protests are due within 10 days of the last publication. The director can reject or condition an application whether or not anyone protests, if the use would:
- reduce the water under existing rights;
- draw on an insufficient supply;
- be made in bad faith or for speculation;
- be beyond the applicant's financial resources;
- conflict with the local public interest;
- be contrary to conservation;
- hurt the local economy of the source watershed, when the water leaves it.
In much of southern Idaho, new consumptive rights are hard to get at all. IDWR's amended Snake River Basin moratorium order, dated July 16, 2024, suspends processing of new applications for consumptive use of surface and ground water in large parts of the basin. Exempt from the suspension: domestic use, non-consumptive uses, replacement wells and transfers of existing rights. Municipal and community water system applications are presumed fully consumptive unless the applicant rebuts that with detailed evidence, including monitoring and mitigation commitments. The director can approve an otherwise barred application case by case if it serves the public interest or will not affect prior rights because of mitigation or insignificant consumption.
The 2026 data center cooling law
House Bill 895, signed April 2, 2026, added Idaho Code 42-252. A data center (as the sales tax statute defines one) that begins construction on or after July 1, 2026 may not use water for cooling as a consumptive use unless the water is supplied by a municipal, water district, or water and sewer district system. The bill's findings tell the IDWR director that, for new appropriations and transfers, data center water use conflicts with the local public interest and is contrary to conservation. So for evaporative cooling, the private-well and farm-transfer paths below are close to shut, and the city contract becomes the main road. Closed-loop and dry designs that consume little water are less affected. Ask which cooling design a project plans before you decide which path applies.
Transfers
Where new rights are closed, the path is buying an existing right, usually irrigation, and changing it. Idaho Code 42-222 lets IDWR approve a change only if it causes no injury to other rights, does not enlarge the original use, is consistent with conservation and the local public interest, and is a beneficial use. And one clause matters a lot in farm country: the director shall not approve a change away from agricultural use that would significantly affect the agricultural base of the local area. Transfers get the same 10-day protest window after notice.
A transfer is also a public record of who bought whose water. If an LLC buys a farm and files to change its right from irrigation to industrial, that filing may be the first document that names the project's water plan.
Reclaimed water
Treated city wastewater can feed cooling systems that would otherwise use drinking water. It is the usual answer when residents worry about wells. Questions: Does the pipeline exist, or is it planned? Is the effluent already committed to another reuse or to a river discharge someone downstream relies on? What happens in winter, when cooling needs fall but effluent keeps flowing, or in summer, when the reverse happens? Tucson's Project Blue offered reclaimed water after two years on potable supply; the council rejected the deal in August 2025 anyway.
Units, and the math that matters
| Unit | Equals |
|---|---|
| 1 acre-foot | 325,851 gallons |
| 1 cubic foot per second (cfs) | about 448.8 gallons per minute, or about 646,317 gallons per day |
| 1 million gallons per day (MGD) | about 1.55 cfs, or about 1,120 acre-feet per year |
Example: Tamarack's water request
Project Tamarack asks the invented city of Halcott Springs for 400,000 gallons a day on average and 1,100,000 on its peak day.
- Annual volume: 400,000 x 365 = 146,000,000 gallons. Divide by 325,851: about 448 acre-feet a year.
- Peak rate: 1,100,000 / 646,317 = about 1.70 cfs. In gallons per minute: 1,100,000 / 1,440 = about 764 gpm.
- Household comparison: EPA WaterSense says an average American family uses more than 300 gallons a day at home. 400,000 / 300 = about 1,330 families on an average day.
Now the city side. Halcott Springs can produce 6.0 million gallons on its peak day. Its current peak is 4.8 million.
- Spare peak capacity: 6.0 minus 4.8 = 1.2 million gallons.
- Tamarack's peak request as a share of spare: 1.1 / 1.2 = about 92 percent.
- If the city's own demand grows 2 percent a year: 4.8 x 1.02 = 4.896 after one year, 4.8 x 1.02^3 = about 5.09 after three. By year three, spare capacity is 6.0 minus 5.09 = 0.91 million gallons, less than Tamarack's peak.
So the deal needs a new well or a curtailment clause within three years. Someone pays for that well. The water service agreement should say who.
Compare Lancaster, Pennsylvania's community benefits agreement, which caps municipal water at 20,000 gallons a day per campus and requires closed-loop cooling. The site's previous user averaged 100,000 to 125,000 gallons a day. A cap like that is a design choice, usually dry or closed-loop cooling that trades water for more electricity on hot days.
What belongs in a water service agreement
Checklist
- Average-day and peak-day quantities, with a hard cap and metering
- Priority in shortage: does the data center get cut before, with or after residents?
- Who pays for new wells, storage, pipes and treatment, and when
- Rate: same as other industrial customers, or a special rate? Is it below cost?
- Cooling design commitment (closed-loop, dry, evaporative) and what triggers a change
- Reclaimed water: start date, who builds the line, what happens if it slips
- Wastewater: volume, temperature and chemistry of blowdown discharged to the sewer
- Annual public reporting of actual use against the cap
- Term, renewal and what happens if the site is sold
Common mix-ups
- Claim: The city has water rights, so supply is not a question. What the evidence shows: Rights held for future needs are not the same as wells, pumps and treatment capacity on a peak day. Ask for peak-day capacity and current peak.
- Claim: A data center can just drill a well. What the evidence shows: It needs an IDWR permit, and in moratorium areas new consumptive rights are suspended. And since July 1, 2026, Idaho Code 42-252 bars a new data center from consumptive cooling use of any water that a municipal or district system does not supply.
- Claim: Buying a farm's water right is a private matter. What the evidence shows: A change of use needs IDWR approval after public notice, and the director must consider injury, enlargement and the local agricultural base.
Reporting angle
- Request the will-serve letter, the capacity study behind it and any draft water service agreement from the city.
- Search IDWR's water right records for the parcel, the LLC and the seller. Look for new applications and transfers.
- Read IDWR legal notices in the local paper and on IDWR's site; the protest window is only 10 days.
- Ask the city for its peak-day production and current peak, and do the spare-capacity math yourself.
- Ask whether the reclaimed water is already promised to anyone else.
- After opening, request annual metered use and compare it with the cap.
Research angle
- Idaho Code 42-252: Limits on consumptive water use by data centers.
- Idaho Code 42-203A: Notice and protest of water right applications.
- Idaho Code 42-222: Changes to a water right.
- IDWR amended Snake River Basin moratorium order: The July 2024 order.
- 2026 House Bill 895: The bill text with its findings.
Check yourself
1. Under Idaho Code 42-203A, how long do people have to protest a new water right application after the last publication of notice?
Protests are due within 10 days of the last date of publication. Notice runs once a week for two successive weeks.
2. A data center needs 400,000 gallons a day on average. About how many acre-feet is that per year?
400,000 x 365 = 146 million gallons. Divide by 325,851 gallons per acre-foot: about 448 acre-feet.
3. Under Idaho Code 42-202B, when does industrial water use count as a municipal purpose?
Municipal purposes include industrial use supplied by a municipal provider within its service area, which is one reason annexation and water often travel together.
4. Which of these did IDWR's amended Snake River Basin moratorium order (July 2024) exempt from its suspension of new consumptive applications?
Transfers, domestic uses, non-consumptive uses and replacement wells are exempt. Municipal applications are presumed fully consumptive unless the applicant rebuts that with detailed evidence.
5. What standard must IDWR apply before approving a transfer that moves water away from agricultural use, under Idaho Code 42-222?
The statute bars injury and enlargement, requires consistency with conservation and the local public interest, and bars changes from agriculture that would significantly affect the local agricultural base.
6. A city's peak-day capacity is 6.0 million gallons and its current peak is 4.8 million. A data center asks for 1.1 million gallons on its peak day. What share of the city's spare peak capacity is that?
Spare capacity is 6.0 minus 4.8 = 1.2 million gallons. 1.1 / 1.2 is about 92 percent.
Terms in this lesson
- Prior appropriation
- The Western water law rule that the earliest water right on a source is served first in a shortage: first in time, first in right.
- Acre-foot
- The volume that covers one acre one foot deep: 325,851 gallons.
- Cubic foot per second (cfs)
- A flow rate of one cubic foot of water passing each second, about 448.8 gallons a minute or 646,317 gallons a day.
- Will-serve letter
- A letter from a water or sewer provider saying it can and will serve a proposed project, usually with conditions.
- Water right transfer
- An IDWR-approved change to an existing water right's point of diversion, place of use, purpose or season.
- Moratorium (water)
- An IDWR order suspending processing of new applications to appropriate water in a stated area.
Sources
- Idaho Code 42-203A, Notice and protest of applications checked 2026-10
- Idaho Code 42-252, Limitations on consumptive use, data centers (2026, ch. 291) checked 2026-10
- Idaho Legislature, 2026 House Bill 895 (legislative findings) checked 2026-10
- Idaho Code 42-222, Change in point of diversion, place, period or nature of use checked 2026-10
- Idaho Code 42-202B, Definitions (municipal purposes, municipal provider, reasonably anticipated future needs) checked 2026-10
- IDWR, Amended Snake River Basin Moratorium Order (July 16, 2024) checked 2026-10
- City of Lancaster, PA, About the Community Benefits Agreement (water cap) checked 2026-10
- EPA WaterSense, How We Use Water checked 2026-10
- Idaho Code 50-222, Annexation by cities checked 2026-10