Lesson 9 of 9 · about 19 minutes
The Checklist, and the Case For and Against Hosting
You'll be able to
- Use a checklist of questions and records at each approval step
- State the strongest local-planning argument for hosting a data center, with named sources
- State the strongest local-planning argument against, with named sources
- Separate factual disputes a record can settle from value disputes a vote has to settle
Everything in this module comes down to two jobs. One is knowing what to ask for at each step, so that the decision rests on documents instead of a slide deck. The other is weighing the result honestly. The checklist below handles the first. The second half of the lesson lays out the strongest planning-level arguments on each side.
The step-by-step checklist
| Step | Questions to ask | Records to request | Where |
|---|---|---|---|
| Land option and purchase | Who is the buyer? What else has it bought? Price per acre versus recent sales? | Deeds, recorded options, LLC filings, registered agent and organizer | County recorder; Secretary of State |
| Early talks | Who signed NDAs, when do they expire, and do they carve out records law? | NDAs and signer lists; calendars; emails by code name and LLC | County and city; economic development office |
| Utility request | How many MW, by what year? Which phase? Applied to other utilities? | Any filed special contract or tariff request; utility load forecast | Idaho PUC case search; utility resource plan |
| Annexation | What services will the city provide, at whose cost? What zoning comes with it? | Annexation plan; notices; consent forms | City clerk; planning department |
| Rezone, special use permit or text amendment | Which use category? Which parcels does a text amendment reach? Setbacks and height? | Application, site plan, staff report, notice proofs and mailing list | Planning department |
| Conditions | Each condition: what number, measured how, where, by whom, with what consequence? | Noise study with inputs; lighting plan; generator specs; decommissioning estimate | Planning department; hearing packet |
| Development agreement or CBA | Recorded? Binds successors? Remedies, cure periods, security? | Every draft; date first received; final recorded version | County clerk and recorder |
| Tax incentives | Which exemptions? Which taxing districts lose what? Clawback and security? | 63-602NN application and notice to districts; assessor projections; incentive agreement | County clerk; assessor; company |
| Water | Average and peak day? Source? Priority in shortage? Who pays for new wells? | Will-serve letter; capacity study; water service agreement; IDWR applications or transfers | City utility; IDWR |
| Air permit | How many engines, what tier, what testing schedule? Comment period? | Permit to construct application with modeling; draft permit | Idaho DEQ |
| Power contract review | Minimum bill, term, exit fee, collateral, who pays for each cost bucket? | Application, staff comments, intervenor testimony, order | Idaho PUC |
| Construction | Haul routes, road repair, worker housing? | Road use agreement; pre-construction road survey; building permits | Road agency or highway district; building department |
| Operation | Did the promises hold? | Noise verification; generator logs; metered water; job reports; CBA annual report | County, city, DEQ, company |
Records requests under Idaho law carry working-day deadlines, so the date each request went in matters. The Idaho Open-Meetings Compliance Tracker keeps the meetings in view, and the Idaho FOIA / Public Records Letter Generator formats the requests.
The case for hosting, at full strength
The broad national case was laid out in the case for and against lesson of the impacts module. Here is the version a supporter would make at a county planning table.
A large tax base that asks little in return. Virginia's Joint Legislative Audit and Review Commission found in 2024 that in five localities with mature data center markets, data center revenue ranged from under 1 percent to 31 percent of total local revenue. A campus sends no children to school and, after construction, adds little traffic. In Idaho's budget-based property tax system, new taxable value spreads the same budget over a bigger base. In lesson 6's invented county, a fully taxable $1.2 billion campus cut a typical homeowner's county tax by about $357 a year.
Conditions and agreements can handle the physical impacts. Supporters point to places that wrote strong terms and still got projects. Kent County, Delaware's July 2026 ordinance set 300- and 400-foot setbacks, a 55-decibel property-line limit, weekday daytime generator testing and 100 percent decommissioning security. Lancaster, Pennsylvania got $20 million in community funds, a 20,000-gallon-a-day water cap per campus and an ambient noise standard, with no city tax breaks. The argument: say yes with teeth, instead of no.
Measurable local economic gains. Dany Bahar and Greg Wright, in a Brookings analysis updated August 2026, compared counties that got large data centers with counties whose announced projects were canceled. They found data processing employment up about 56 percent and telecommunications employment up about 43 percent over the first decade.
Ratepayer protection can be written. In the Brisbie LLC case, Idaho PUC staff found that transmission costs up to the delivery point would not be borne by other ratepayers, and the commission added further safeguards before approving the contract. A county that intervenes at the PUC can push for more.
The case against hosting, at full strength
The biggest costs are the hardest to fence off. Ari Peskoe and Eliza Martin of Harvard's Environmental and Energy Law Program, after reviewing nearly 50 proceedings, argued that special contracts often shift data center power costs onto other ratepayers. JLARC estimated a typical Dominion residential customer's generation and transmission costs could rise $14 to $37 a month by 2040 under strong data center growth. A substation can be charged to the customer; shared lines and new power plants are divided by cost-of-service methods, and in Idaho that method is being argued right now in IPC-E-26-07, where the Idaho Irrigation Pumpers Association asked for a technical hearing.
Decisions get made before the public arrives. FAS found that data center CBAs are often negotiated behind closed doors under NDAs, and could get some of them only through records requests. In Arizona, a county NDA was described as covering all 7,000 county employees. In Lancaster, a community group said it got the draft agreement two days before the vote. By the time a hearing opens, the land is bought, the utility studies are done and the incentive talks are well along.
The land and water commitments are long. A campus fixes land use for decades. In Virginia, the American Battlefield Trust campaigned against the Prince William Digital Gateway to protect Manassas National Battlefield Park, and a court later voided the rezoning over notice defects. In Idaho, new consumptive water rights are suspended across much of the Snake River basin, so new supply often has to come from transfers out of irrigation. Idaho Code 42-222 bars transfers that would significantly affect a local agricultural base, and the 2026 law in Idaho Code 42-252 goes further for data centers: consumptive cooling water for a new one must come from a municipal or district system, with legislative findings that data center water use conflicts with the local public interest.
Few jobs and quiet costs. Idaho's sales tax exemption requires 30 permanent jobs for $250 million of investment. The same Brookings study that found data processing job gains found no change in wages and home prices up 2 to 5 percent, which helps owners and hurts renters and first-time buyers. And as lesson 6 showed, an exemption's cost in Idaho shows up as tax relief residents didn't get, which rarely gets noticed.
The third answer: wait
Some places have answered with not yet. The Data Center Knowledge roundup of April 14, 2026, by Nathan Eddy, collected the pause proposals and the arguments around them.
| Proposal | What it would do | Status |
|---|---|---|
| Artificial Intelligence Data Center Moratorium Act (Sen. Bernie Sanders; Rep. Alexandria Ocasio-Cortez in the House) | Halts construction or upgrades of AI data centers, defined as AI work "at scale" or over 20 MW with dense racks or liquid cooling, until Congress passes laws on federal pre-release review of AI, worker protections, no bill increases, no subsidies, community approval and union labor | Proposed; draft text posted by Sen. Sanders' office |
| Maine LD 307 | Temporary statewide moratorium on data centers over 20 MW through November 2027, plus a coordination council | Passed the Legislature; Gov. Janet Mills vetoed it April 24, 2026 because it did not exempt a project at the former paper mill site in Jay; the override failed April 29 |
| Local fights, no formal moratorium | Microsoft's proposed Caledonia, Wisconsin campus | Halted after local opposition |
Mills' veto letter is the interesting part. She agreed a moratorium was appropriate, citing environmental and rate impacts, and said she would have signed the bill with the exemption. So the fight in Maine came down to one project's carve-out.
The two sides of a pause look like this. For it: Mary Johnston Turner of the research firm IDC told Data Center Knowledge the proposals reflect real worries about affordability, quality of life and sustainability, while saying it is too early to judge the effect on buildout. The pressure is measurable. The article cites Data Center Watch for at least 36 projects delayed or blocked between May 2024 and June 2025, an estimated $162 billion in investment; Data Center Watch's report page, as fetched for this course, still shows its earlier tally of $64 billion through March 2025, so cite whichever version you can see and its date. Against it, or at least for a different fix: Amit Narayan of GridCare argued the bottleneck is underused grid capacity, not a lack of power, and Wannie Park of Pado AI warned that pauses raise execution risk, can strand capital and push builders toward friendlier states. Industry is already adjusting with self-powered campuses; a Bloom Energy report found a third of hyperscalers and colocation providers plan fully self-powered campuses by 2030, which moves the power question out of the utility commission and into air and land permits.
For an Idaho county, the pause tools are the emergency and interim moratoriums in Idaho Code 67-6523 and 67-6524, covered in the energy siting course lesson Moratoriums, and the Limits on Public Land. They buy months, not years, which suits the use Maine's governor endorsed: time to write rules, not a permanent ban.
Sorting the disputes
| Question | Factual or values? | What could settle or narrow it |
|---|---|---|
| Will nighttime noise at the nearest home exceed 45 dBA? | Factual | Modeled study before approval; measurement after |
| Will other customers pay for the power supply? | Factual, with uncertainty | PUC cost-of-service testimony, contract terms, final order |
| Is there water on the hottest day of a dry year? | Factual | City peak-day capacity; IDWR records; shortage priority in the contract |
| Would the project come without the tax break? | Factual, hard to know | Site selection records, company statements, other states' studies |
| Should this valley host an industrial campus? | Values | Public process, comprehensive plan, elections |
Where the evidence is clear, say so. Physical impacts like noise, light and generator exhaust can be limited by well-written, enforced conditions. Ratepayer risk depends on contract terms and cost allocation that are on the public record at the PUC. Water supply in much of southern Idaho is tight, and the law already treats transfers out of farming with caution. Job counts are small relative to investment. Whether the trade is worth it is a values question, and anyone arguing either side should say so plainly.
Common mix-ups
- Claim: Supporters just want the money and opponents just hate change. What the evidence shows: Irrigators, industrial customers, cities, conservation groups and county budget officers each have documented, specific interests. Both the interest and the evidence are usually on the public record.
- Claim: The zoning vote is the whole decision. What the evidence shows: Rates, air permits, water rights and the state sales tax exemption are decided elsewhere. The checklist above has thirteen rows for a reason.
Reporting angle
- Publish the checklist for a real project with every record linked and every gap marked "requested" or "not yet filed."
- Interview one person on each side and ask each for the single document that best supports their position. Print both.
- Label values disputes as values disputes. Do not ask a noise study to settle whether a valley should change.
- Give readers the next decision dates on every track: hearing, comment deadline, PUC schedule, DEQ notice.
- If a moratorium is proposed, ask what rules the pause is meant to produce and by what date, request the draft findings, and check whether any pending application would be exempted, the issue that sank Maine's LD 307.
- Ask Idaho's members of Congress where they stand on the Sanders moratorium bill and on federal permitting help for data centers. Both are on the table at once.
Research angle
- JLARC, Data Centers in Virginia: The 2024 state legislative review.
- Brookings on employment effects: Evidence on jobs.
- Harvard EELP paper: How ratepayers can end up paying for large loads.
- Idaho PUC case IPC-E-26-07: The case summary page with filings.
- Idaho Code 42-252: Limits on consumptive water use by data centers.
- City of Lancaster community benefits agreement: The agreement and its terms.
- Data Center Knowledge on moratorium proposals (April 14, 2026), the Sanders moratorium bill text, and the Data Center Watch report on blocked and delayed projects.
- Maine LD 307: Route Fifty on the veto and WABI on the failed override; the bill and veto letter are on the Maine Legislature's site.
Pictures, Numbers and Infographics
Power, water and paperwork set the pace for a data center in Idaho. The state's electricity is cheaper than the national average, and Idaho already buys more power than its own plants generate.
By the numbers
- 9.51 cents: Idaho's average retail price of electricity per kilowatt-hour in 2024, against 12.94 cents for the United States as a whole. U.S. Energy Information Administration, Idaho Electricity Profile 2024
- 20,035,438 MWh against 26,369,555 MWh: electricity generated in Idaho in 2024 compared with electricity sold to Idaho retail customers. The state already uses more than its own plants produce. EIA, Idaho Electricity Profile 2024
- 90 percent: the load factor Idaho Power expected from Brisbie, a data center customer the order describes as becoming the utility's largest. Under the contract terms reviewed, the first 20 MW of energy load were priced at Schedule 19T rates and load above that at a marginal cost rate. Idaho PUC Order No. 35777, case IPC-E-21-42, 2023
- 100 hours a year: the most an emergency backup engine may run for maintenance and readiness testing under the federal engine rule. Up to 50 hours of non-emergency use count inside that 100. EPA rule, 40 CFR 63.6640(f)
- More than 300 gallons: water the average American family uses at home each day, a yardstick for reading a data center's gallons-per-day request. EPA WaterSense
- 10 days: time to file a protest after the last published notice of a new water right application. Idaho Code 42-203A
- 3 and 10 working days: an Idaho agency must grant or deny a records request within 3 working days, or, if it gives written notice that it needs longer, provide the records to a resident within 10 working days. Idaho Code 74-103
Check yourself
1. At the rezone or special use permit step, which record best shows what the county will actually require of the developer?
The staff report lists proposed conditions, and the draft development agreement shows the recorded commitments that would bind later owners.
2. Which source supports the argument that data centers can carry a large share of a local tax base?
JLARC's local revenue figures are the main evidence for the tax-base argument.
3. Brookings researchers Dany Bahar and Greg Wright compared counties that got large data centers with counties whose announced projects were canceled. What did they find on wages and home prices?
They found data processing employment up about 56 percent over the first decade, no wage change and home prices up 2 to 5 percent.
4. A resident says, 'Even with every condition met, I don't want a 300-acre industrial campus in this valley.' What kind of dispute is that?
No document can prove a preference wrong. Calling it a values question keeps the factual arguments honest.
5. Which Idaho water law provision reflects the concern that data centers could pull water out of farming?
The transfer statute includes that agricultural base limit alongside the no-injury and no-enlargement tests.
6. What is the most useful first question for a commissioner who says the data center will 'protect ratepayers'?
Ratepayer protection is decided at the state utility commission, so the claim can only be checked against that case.
Terms in this lesson
- Values dispute
- A disagreement about what matters or what a place should be, which evidence can inform but cannot settle.
- Factual dispute
- A disagreement about what is true or likely, which records, studies or measurement can settle or narrow.
- Staff report
- The planning staff's written analysis of an application, usually with recommended findings and conditions, posted before a hearing.
- Intervention
- Becoming a formal party in a utility commission case, with the right to file testimony; open to governments and groups as well as companies.
Sources
- JLARC, Data Centers in Virginia (2024) checked 2026-10
- Brookings, New evidence on data center employment effects (Bahar and Wright, updated Aug. 10, 2026) checked 2026-10
- Harvard EELP, Extracting Profits from the Public (Peskoe and Martin, March 2025) checked 2026-10
- City of Lancaster, PA, About the Community Benefits Agreement checked 2026-10
- Technical.ly, Delaware county adopts new zoning for data centers (July 23, 2026) checked 2026-10
- Federation of American Scientists, data center community benefit agreements (2026) checked 2026-10
- American Battlefield Trust, Stop Prince William Digital Gateway and protect Manassas Battlefield checked 2026-10
- Idaho PUC, IPC-E-21-42 Final Order No. 35777 (May 11, 2023) checked 2026-10
- Idaho PUC, Case IPC-E-26-07 summary page checked 2026-10
- Idaho Code 42-222, Changes to water rights checked 2026-10
- Idaho Code 42-252, Limitations on consumptive use, data centers (2026) checked 2026-10
- Data Center Knowledge: AI data center moratoriums, balancing energy, community and growth risks (Nathan Eddy, April 14, 2026) checked 2026-10
- Sen. Bernie Sanders: Artificial Intelligence Data Center Moratorium Act, draft bill text checked 2026-10
- Data Center Watch: Local activism threatens to derail the U.S. data center boom (report page) checked 2026-10
- Route Fifty: Maine governor vetoes landmark data center ban (April 2026) checked 2026-10
- WABI: Maine Legislature does not override Gov. Mills' veto of data center moratorium (April 29, 2026) checked 2026-10