🏛️ Issues and Advocacy Training
Courses › Supplemental Nuclear: Small Modular Reactors

Lesson 1 of 9 · about 15 minutes

What makes a reactor small or modular

You'll be able to

  • Define a small modular reactor and a microreactor and give real examples of each as of October 2026
  • Explain the two different meanings of 'modular'
  • Convert thermal megawatts to electric megawatts and catch a pitch that mixes them
  • Size a fleet of small reactors for a large load, including refueling and backup margin

A large U.S. reactor like Vogtle Unit 4 sends out about 1,114 megawatts of electricity. A small modular reactor is usually defined as 300 MWe or less per unit. A microreactor is smaller again, from a few kilowatts up to roughly 20 MWe. Those lines come from convention, mostly the International Atomic Energy Agency's working definitions, and no U.S. law draws them. So a company can call a 340 MWe unit "small," and Holtec does exactly that with its SMR-300.

The SMRs and advanced reactors lesson in the Nuclear Power course gave the licensing steps and a first status table. This course goes further into the designs, the Idaho work, water, fuel and waste. Start with the vocabulary, because most confusion at public meetings starts there.

Two meanings of "modular"

The word does double duty, and pitches slide between the meanings.

  • Factory-built modules. Large pieces of the plant (reactor vessel sections, steel-and-concrete wall rings, piping skids) are made in a factory and shipped. The hope is assembly-line quality and speed. Ontario Power Generation's first BWRX-300 at Darlington is being built with steel composite wall rings and a basemat lifted into a shaft in April 2026.
  • Multi-module plants. Several identical reactors share one site. NuScale's US460 design, approved by the NRC in May 2025, is six 77 MWe modules for 462 MWe. X-energy's Long Mott plan for Dow is four Xe-100 units totaling 320 MWe, about 80 MWe each.

A plant can be one, both or neither. A single BWRX-300 is a factory-heavy design but one reactor. A six-module NuScale plant is both. When someone says "modular," ask which one they mean, because the cost argument depends on it. Factory savings require many orders of the same design. Multi-module savings come from sharing staff, security and a control room.

The size ladder

DesignElectric outputClassStatus note, October 2026
MARVEL (DOE, at INL)About 10 kWe (85 kWt)Test microreactorPrimary vessel arrived in Idaho; criticality planned for 2027
Radiant Kaleidos1 MWe (3.5 MWt)MicroreactorFuel delivered to INL's DOME test bed July 2026
Westinghouse eVinci5 MWe (15 MWt)MicroreactorZero-power criticality experiment on a scaled mock-up of its core, in Nevada, reported August 2026
Aalo-X10 MWeMicroreactorCritical test reactor reached criticality at INL July 4, 2026
BWXT BANR20 MWe (75 MWt)Upper edge of microPicked for the Army's Janus program at Fort Campbell, August 2026
Oklo AuroraUp to 75 MWeSmallUnder construction at INL under DOE authorization
NuScale module77 MWe each, 6 per plantSmall, multi-moduleNRC standard design approval May 2025
X-energy Xe-100About 80 MWe each, 4 per plantSmall, multi-moduleConstruction permit decision pending at the NRC
GE Vernova Hitachi BWRX-300Up to 300 MWeSmallUnder construction in Ontario; U.S. permit issued to TVA, September 2026
TerraPower Natrium345 MWe, up to 500 MWe with salt storageSmall by conventionConstruction began in Wyoming April 2026
Holtec SMR-300About 340 MWe eachCalled smallPartial construction permit application accepted by the NRC in 2026

Lesson 3 of this course gives the licensing status for each with dates. For now, notice how wide the range is. The smallest unit on this list would need more than 100,000 copies to match one Vogtle reactor. The largest is about a third of one.

What microreactors are trying to be

Microreactors are less about the grid and more about places the grid doesn't reach well. The design goals show up again and again in company literature: factory-assembled and shipped whole (Kaleidos fits in one standard shipping container), fueled at the factory, run for years without refueling, then shipped back. The NRC's Part 53 rule, published March 30, 2026, includes a provision for factory fuel loading into manufactured reactors (10 CFR 53.620), which is the regulatory piece that business model needs.

Customers they name: military bases that want power if the local grid goes down, remote mines and Arctic towns that now burn diesel, disaster recovery, and in the last two years, data centers. Lesson 2 sorts the designs by purpose.

Thermal versus electric

Reactors make heat. Only part of that heat becomes electricity, and the rest goes to the air or water. The ratio is the conversion efficiency, and it depends on how hot the coolant runs and what kind of turbine or engine is used. Here are the published pairs:

Example: checking the ratio

  • eVinci: 5 MWe ÷ 15 MWt = 0.33, or 33 percent.
  • Kaleidos: 1 MWe ÷ 3.5 MWt = 0.29, or 29 percent.
  • BANR: 20 MWe ÷ 75 MWt = 0.27, or 27 percent.
  • MARVEL: 10 kWe ÷ 85 kWt = 0.12, or 12 percent. It is a test bed, built to answer questions, not to convert heat well.

So a "75 megawatt" reactor could mean BANR's 75 MWt, which is 20 MWe, or Oklo's Aurora at up to 75 MWe. Those differ by almost a factor of four in electricity. And whatever is not converted has to be rejected as waste heat, which is the subject of lesson 7.

Sizing a fleet for a big load

Data center developers talk about reactors as if one reactor equals one campus. It doesn't work that way, because reactors stop for refueling and maintenance, and a single trip would black out a campus with no backup.

Example: Project Juniper in Copper Flats

An invented data center campus, Project Juniper, wants 300 MW of steady power. The developer is looking at 80 MWe modules. Assume each module averages 91 percent of its full output over a year, the capacity factor the EIA reports for the existing U.S. fleet in 2025.

  • Average output per module: 80 × 0.91 = 72.8 MW.
  • Modules needed to average 300 MW: 300 ÷ 72.8 = 4.12, so 5 modules (you can't build 0.12 of one).
  • Now plan for one module tripping offline at the worst moment. Four remaining modules at full output give 4 × 80 = 320 MW, which covers 300 MW only if none of the four is down for refueling at the same time.
  • A cautious plan is 6 modules, or 5 modules plus a grid connection for backup.

So "four reactors for our 300 MW campus" in a press release usually means the grid is still the backup. That matters to everyone else on that grid, because someone has to keep that backup capacity ready.

Why "supplemental"

Almost no SMR plan replaces the grid. They add to it, in roughly these arrangements:

  • Grid-connected: the reactor sells into the grid like any plant (TVA's Clinch River, Darlington).
  • Co-located or behind the meter: the reactor sits next to a customer and serves it directly, with or without a grid tie (Dow's Long Mott plan for industrial steam and power; Aalo's stated plan to power a co-located data center).
  • Islanded: no grid at all, as with a remote mine or a base that wants to ride out an outage.

Each type raises different public questions. Grid-connected plants go through utility commissions and their costs can reach ratepayers. Behind-the-meter deals may skip much of that review, which is good for speed and bad for public oversight. The costs and timelines lesson covers who carries the risk.

Common mix-ups

  • Claim: SMR means a reactor under 300 MW, by law. What the evidence shows: It is a convention. Holtec calls its roughly 340 MWe units SMRs, and the NRC licenses them under the same rules as any power reactor.
  • Claim: A microreactor can power a city. What the evidence shows: At 1 to 20 MWe, a microreactor serves a base, a mine, a hospital campus or a small town. A city needs hundreds or thousands of megawatts.
  • Claim: Modular means cheap. What the evidence shows: Modular is a construction strategy. Cost savings depend on many repeat orders, which no SMR design has yet had in the U.S.

Reporting angle

  • When a reactor proposal appears, write down four numbers from the developer: MWe per unit, number of units, MWt per unit and expected capacity factor. If they can't give them, the project is early.
  • Ask whether the plant will be grid-connected, behind the meter or islanded. That decides whether your state utility commission sees it at all.
  • Ask what the backup is when a unit is down for refueling. If the answer is "the grid," ask which utility has agreed to provide it and on what tariff.
  • Ask which design, by vendor and model name. A proposal that has not picked a design can't give honest water, waste or emergency planning numbers.
  • Watch county and city agendas for land-use applications, annexations and water right transfers. These often surface before any NRC filing.

Research angle

  • The IAEA's SMR topic page gives the up-to-300 MWe working definition used internationally. Microreactor size lines vary by source.
  • The NRC's advanced reactors pages list designs in pre-application and under review, with links to licensing dashboards.
  • Vendor specification pages, such as GE Vernova's BWRX-300 page, give official output numbers. Compare them with what the NRC docket says.
  • The Part 53 rule page lists provisions written with factory-built reactors in mind.
  • For capacity factors of the existing fleet, use the EIA's Electric Power Monthly, and see the capacity factor lesson.

Check yourself

1. Westinghouse lists the commercial eVinci at 15 MWt and 5 MWe. What share of its heat becomes electricity?

2. NuScale's US460 plant is 'modular' in which sense?

3. Which of these is a microreactor rather than a small modular reactor?

4. A pitch says a reactor is '75 megawatts.' What should you ask first?

5. Why do developers add more reactors than the bare minimum to serve a data center?

Terms in this lesson

Small modular reactor (SMR)
A reactor of roughly 300 MWe or less per unit, designed for factory fabrication of major parts. The line is a convention, not a legal limit.
Microreactor
A very small reactor, from a few kilowatts to roughly 20 MWe, often designed to be shipped whole and run for years without refueling.
MWt and MWe
Megawatts thermal (heat made in the core) and megawatts electric (power sent out). MWe is always the smaller number.
Multi-module plant
A plant made of several identical small reactors sharing one site, control room and support systems.
Supplemental power
Generation added alongside the existing grid supply, either feeding the grid or serving one customer behind the meter.

Full glossary

Sources