Lesson 2 of 9 · about 18 minutes
The Grid Side: Queues, Tariffs and Who Pays
You'll be able to
- Explain how regulated utilities recover the cost of new generation and transmission from customers
- Describe the main features of a large-load tariff: minimum demand charges, contract terms, exit fees and collateral
- Summarize real 2025 and 2026 large-load decisions in Ohio, Virginia and Texas, and the open Idaho case
- Find and read a state utility commission docket
A data center cannot plug in like a house. It has to ask the utility for service, wait for engineering studies, and sign a contract. In a regulated state, the terms of that contract go before the state utility commission. That process is where the money question gets settled: if the utility builds a substation, a transmission line or a power plant to serve one customer, who pays for it?
How utilities recover costs
Most of the country is served by investor-owned utilities regulated by a state commission. The basic deal is old and simple. The utility builds what the system needs. The commission decides whether the spending was prudent. If it was, the utility recovers the cost, plus an approved return on investment, from all customers through rates. A cost of service study divides those costs among customer classes: residential, small commercial, large industrial, irrigation and so on.
That model assumes growth benefits everyone, because a bigger system spreads fixed costs over more sales. A huge new customer can lower rates for others if it pays its share and stays for decades. It can raise them if the utility builds for it and the customer pays too little, shrinks or leaves. Both outcomes are possible. The contract terms decide which one happens.
Ari Peskoe and Eliza Martin of the Harvard Environmental and Energy Law Program reviewed nearly 50 regulatory proceedings in a March 2025 paper and argued that special contracts and discounted rates often shift data center costs onto other ratepayers. Utilities and the industry answer that new large-load tariffs are designed to stop exactly that. Both claims can be tested case by case, and the docket for each case is where the evidence sits.
The queue
Before any of that, a project waits in line. Generator queues are better documented than load queues. LBNL's Queued Up: 2026 Edition counted more than 2,060 GW of generation and storage seeking connection at the end of 2025. Projects built in 2025 took a median of more than five years from request to operation, and only 13 percent of capacity that applied from 2000 to 2020 had reached operation by the end of 2025. New power plants that might serve data centers face that same line.
Large loads have had less standard treatment. In October 2025 the Secretary of Energy directed the Federal Energy Regulatory Commission to consider rules for connecting loads above 20 MW directly to FERC-jurisdictional transmission (Docket RM26-4). The advance notice floated study deposits, readiness requirements and having large loads pay 100 percent of assigned network upgrades, and asked for final action by April 30, 2026. On April 16, 2026, FERC said it would act by the end of June. On June 18, 2026, instead of proposing a national rule, it issued show cause orders under Section 206 of the Federal Power Act directing six regional grid operators (PJM, MISO, SPP, CAISO, ISO New England and NYISO) to address large-load interconnection in their own rules. Idaho Power is outside those markets. Check FERC eLibrary for the latest filings before you cite a status. Retail rates stay with the states in any case.
What a large-load tariff contains
Regulators have converged on a toolkit. Not every tariff has every item, and Idaho Power's own 2026 investor slides say approved agreements are "evaluated on a case-by-case basis."
| Term | What it does | Who it protects |
|---|---|---|
| Minimum demand charge (take-or-pay) | Customer pays for a set share of contracted capacity even if it uses less | Other customers, if the load underperforms |
| Long contract term | Locks in payments for 10 to 20 years | Other customers, against stranded plants |
| Exit or termination fee | Customer pays remaining costs if it leaves early | Other customers |
| Collateral or credit support | Letter of credit or guarantee scaled to project risk | Utility and customers, if the developer goes broke |
| Contribution in aid of construction | Customer pays up front for dedicated lines and substations | Other customers |
| Curtailment provisions | Utility can cut the load in emergencies | Reliability for everyone |
Real proceedings, state by state
Ohio
On July 9, 2025, the Public Utilities Commission of Ohio approved AEP Ohio's data center tariff after evidentiary hearings. New data centers above 25 MW must pay for at least 85 percent of subscribed capacity regardless of use, under contracts of up to 12 years with a ramp of up to four years, plus exit fees and financial assurances. Existing sites are grandfathered unless they expand past 25 MW. The industry had backed a softer alternative. The commission sided with the utility's version.
Virginia
Virginia's Joint Legislative Audit and Review Commission estimated in 2024 that a typical Dominion residential customer's generation and transmission costs could rise $14 to $37 a month by 2040, in constant dollars, depending on how much data center growth is built. In November 2025, the State Corporation Commission created a new GS-5 class for customers of 25 MW or more, starting January 1, 2027. They pay a minimum of 85 percent of contracted transmission and distribution demand and 60 percent of generation demand. In the same order the SCC approved residential increases of $11.24 a month in 2026 and $2.36 in 2027, below Dominion's request.
Texas
Governor Greg Abbott signed Senate Bill 6 in June 2025. Loads of 75 MW or more connecting to ERCOT must accept curtailment during firm load-shed events, with shutoff equipment required to connect. The law adds a $100,000 minimum initial interconnection fee, study fees, cost-sharing rules and disclosure of duplicate requests elsewhere in the state.
Idaho
Idaho has no general large-load tariff in statute. Two 2026 bills aimed at one did not become law: SB 1368, which would have required commission approval before serving a customer adding 30 MW or more, failed according to the Idaho Conservation League tracker, and House Bill 609, which would have tied the data center sales tax exemption to rates that fully recover the utility's costs, shows no action past committee referral on the legislature's site. A 2025 bill with a 10 MW threshold, H0395, passed the House and died in a Senate committee.
The live action is at the Idaho Public Utilities Commission:
- IPC-E-26-07, filed March 31, 2026: Idaho Power's petition to review its class cost-of-service method and decide cost-of-service issues for new large-load customers. Intervenors include the Idaho Irrigation Pumpers Association, Micron, the Industrial Customers of Idaho Power, the City of Boise, the Northwest Energy Coalition, Clean Energy Opportunities for Idaho, the Federal Executive Agencies and Bayer (through its affiliate Ruveon LLC). The commission issued a notice of schedule (Order No. 37170) on September 16, and Idaho Power filed direct testimony on September 23, 2026. No decision as of the docket's October 7, 2026 update.
- IPC-E-24-44: a special contract and new Schedule 28 for Micron's memory fab, filed December 6, 2024, approved with modifications in Order No. 37039 on May 8, 2026. Order No. 37092, July 8, 2026, approved Idaho Power's compliance filing with the revised Schedule 28 and an amended contract. It is a chip plant, not a data center, but it sets the template for very large loads on this system.
- IPC-E-22-29: a 200 MW solar purchase agreement serving Brisbie LLC, a Meta affiliate building near Kuna. The application said Brisbie pays all costs of the agreement so other customers are not harmed.
Irrigators have made the cost-shift argument loudest. In a February 2026 guest column in the Idaho Capital Sun, Adam Young, a Bingham County grain and alfalfa grower, reported Idaho Power's demand charge for farmers rising from $6.94 per kW in 2021 to $16.50 in 2026 and argued that new large loads such as data centers and chip plants are the main driver. He quotes Idaho Power as pointing to increased demand and the investment it requires, and he acknowledges residential growth as well. IPC-E-26-07 is where that dispute gets tested with evidence.
Two utilities show the scale. Data centers bought 24 percent of Dominion's Virginia Power electricity sales in 2023, up from 21 percent in 2022, Dominion's 2023 annual report says. In central Washington, Grant County PUD's queue held 2,897 MW of large-load requests in August 2024, 1,568 MW of it from data centers, against a system peak near 1,050 MW (American Public Power Association). By April 2025 the PUD was capping how much more power each data center could take.
Common mix-ups
- Claim: Data centers always raise everyone's rates. What the evidence shows: It depends on contract terms and whether the load shows up as promised. A customer paying full cost on a long contract can spread fixed costs and lower rates. JLARC's Virginia estimate shows real residential increases under high growth.
- Claim: A large-load tariff means residents are fully protected. What the evidence shows: Minimum charges cover some costs and not others. Shared transmission and new generation costs may still be allocated across classes. Read the cost-of-service testimony.
Reporting angle
- Search the state commission's case list for the utility's code plus "special contract," "large load" or "Schedule." In Idaho, case numbers look like IPC-E-26-07.
- Read staff comments, not just the utility's application. Staff often quantify the risk to other customers.
- Note confidential exhibits. Ask the commission what is redacted and why.
- Call intervenors on both sides: irrigators or consumer advocates, and industrial customers.
- Ask: minimum demand percentage, contract length, exit fee, collateral, who pays for the substation?
Research angle
- Idaho PUC case IPC-E-26-07: Large-load docket summary with filings.
- Idaho PUC Order No. 37092: Final order on the Micron special contract.
- Idaho PUC IPC-E-22-29 application: Filing that names the Meta affiliate.
- Mayer Brown on FERC docket RM26-4: Summary of the large load interconnection rulemaking.
- FERC large load docket notice: Agency notice on timing of action.
- POWER on the AEP Ohio tariff: Coverage of a large-load tariff approval.
- Harvard EELP, Extracting Profits from the Public: Peskoe and Martin on who pays for big tech power.
- JLARC Data Centers in Virginia: Virginia's state audit of the industry.
Check yourself
1. Under the AEP Ohio data center tariff approved by the Public Utilities Commission of Ohio in July 2025, new data centers above 25 MW must pay for at least what share of their subscribed capacity?
The tariff requires payment for at least 85 percent of subscribed monthly capacity regardless of actual use, for up to 12 years after a ramp period of up to four years.
2. What is the main purpose of a minimum demand charge in a large-load tariff?
If a utility builds for 500 MW and the customer only uses 200, the minimum charge keeps the cost of the unused build from landing on other customers.
3. Which Idaho Public Utilities Commission case, filed March 31, 2026, asks how to allocate costs for new large-load customers?
IPC-E-26-07 is Idaho Power's petition to review its class cost-of-service methods and address cost-of-service issues for new large-load customers.
4. Texas Senate Bill 6 (2025) requires large loads of 75 MW or more connecting to ERCOT to do what during firm load-shed emergencies?
SB 6 makes large non-critical loads subject to curtailment during firm load shed and requires disconnect capability as a condition of connecting.
5. In the Virginia State Corporation Commission's November 2025 order, the new GS-5 class for customers of 25 MW or more requires minimum payment of what share of contracted generation demand?
The order set 85 percent for transmission and distribution demand and 60 percent for generation demand, starting January 1, 2027.
6. Why is the Idaho Power and Meta Kuna arrangement in case IPC-E-22-29 a useful example of one cost-protection approach?
The filing describes Brisbie LLC, a Meta affiliate, paying all costs of the Pleasant Valley Solar agreement under a special contract.
Terms in this lesson
- Interconnection queue
- The line of projects waiting for a utility or grid operator to study and approve a connection to the grid.
- Large-load tariff
- A rate schedule with special terms for very large new customers, such as minimum bills, long contracts and exit fees.
- Special contract
- A customer-specific agreement between a utility and one large customer, approved by the state commission.
- Cost of service study
- The utility analysis that divides the total cost of running the system among customer classes.
- Integrated resource plan (IRP)
- A long-range utility plan, usually 20 years, showing forecast demand and the plants, lines and programs to meet it.
- Docket
- The official case file at a utility commission, holding every filing, order and public comment.
Sources
- POWER Magazine, Regulator Approves AEP Ohio's Landmark Data Center Tariff checked 2026-10
- Loudoun Now, SCC approves new data center rate class for Dominion (Nov. 25, 2025) checked 2026-10
- Utility Dive, Texas law gives grid operator power to disconnect data centers during crisis (June 25, 2025) checked 2026-10
- Mayer Brown, FERC Large Load Interconnection Preliminary Rulemaking (Docket RM26-4) checked 2026-10
- FERC, FERC to act on large load interconnection docket by June 2026 (Apr. 16, 2026) checked 2026-10
- American Action Forum, FERC data center orders accelerate grid connection (June 2026 show cause orders) checked 2026-10
- Idaho Capital Sun, guest column by Adam Young on farm electric bills (Feb. 23, 2026) checked 2026-10
- Idaho Legislature, H0395 (2025) status page checked 2026-10
- LBNL, Queued Up: 2026 Edition checked 2026-10
- Idaho PUC, Case IPC-E-26-07 summary checked 2026-10
- Idaho PUC, IPC-E-24-44 Final Order No. 37092 (Micron special contract, July 8, 2026) checked 2026-10
- Idaho PUC, IPC-E-22-29 Application (Pleasant Valley Solar PPA for Meta affiliate) checked 2026-10
- Idaho Conservation League, SB 1368: Guardrails for Idaho's Largest Power Consumers (2026) checked 2026-10
- Harvard EELP, Extracting Profits from the Public (Peskoe and Martin, March 2025) checked 2026-10
- JLARC, Data Centers in Virginia (2024) checked 2026-10
- Dominion Energy 2023 annual report (SEC Form ARS) checked 2026-10
- APPA: Grant PUD large-load requests (Sept. 3, 2024) checked 2026-10