🏛️ Issues and Advocacy Training
Courses › Data Centers: Types, Purposes and How They Work

Lesson 9 of 9 · about 15 minutes

Security, Reliability and Why Outages Happen

You'll be able to

  • Describe the layers of physical security at a typical data center
  • Cite Uptime Institute figures on outage frequency, causes and costs
  • Explain why human error and software, not just equipment, cause many outages
  • Read a provider's post-incident report and pull out cause, duration and scope

Most data centers look deliberately boring from the road: a long, windowless building, no sign or a vague one, a tall fence set back from a berm. That is the first layer of security. If a building does not announce what it holds, fewer people get curious.

Layers of physical security

Security people call it defense in depth. An intruder, or a careless contractor, should have to pass several separate barriers before touching a server.

1. Perimeter: fence, berms, bollards, gate, cameras, patrols 2. Building entry: guard desk, ID check, visitor log 3. Mantrap and badge plus biometric 5. Cage or rack lock 4. Data hall access list
Each ring is controlled and logged. Colocation sites add tenant cages so customers cannot reach each other's equipment.
  • Perimeter. Fences, often anti-climb; crash-rated bollards or berms to stop vehicles; a single guarded gate; cameras covering the fence line.
  • Building entry. A staffed security desk, government ID checks, pre-registered visitors only, escort rules.
  • Mantraps. Two interlocking doors so only one verified person passes at a time, stopping tailgating.
  • Badge plus biometrics. Card readers combined with fingerprint, palm vein or iris scans at the data hall doors.
  • Cages and rack locks. In colocation, each tenant's gear sits in a locked cage or rack.
  • Logs and cameras. Every door event is recorded; video is kept for a set period. Auditors for standards such as SOC 2 and ISO/IEC 27001 check these records.
  • Media destruction. Failed drives are shredded or degaussed on site so data never leaves intact.

Physical security also covers the things a building depends on: fuel deliveries, water supply, fiber routes and the substation. A cut fiber bundle at a construction site down the road can do more damage than a person at the front gate, which is why sites insist on fiber entering from different directions.

What the outage numbers say

The Uptime Institute surveys operators every year. The 2025 global survey and the 2026 outage analysis give the clearest picture available, with the usual caution that survey answers are self-reported.

MeasureFigureSource
Operators with an impactful outage in the past three years50% in 2025, down from 53% in 2024 and 74% in 2020Uptime 2025 survey, 2026 outage analysis
Most recent impactful outage rated serious or severeAbout 1 in 10Uptime 2025 survey
Power as cause of most recent impactful outage45% in 2025, down from 54% in 2024Uptime 2026 outage analysis
Most recent major outage cost over $100,00057%Uptime 2026 outage analysis
Most recent impactful outage cost over $1 millionAbout 1 in 5Uptime 2026 outage analysis
Human error at least a minor contributor92%Uptime 2026 outage analysis
Outage preventable with better management, processes or configuration87%Uptime 2026 outage analysis

Outages are becoming less frequent, but the expensive ones are not shrinking, because more of the economy depends on fewer, larger facilities. And the root of most outages is not exotic. A breaker fails and a transfer does not go as planned. Someone skips a step in a procedure. Uptime's 2025 analysis said 85 percent of human-error-related major outages involved staff not following procedures, or procedures that were wrong.

Why redundant systems still fail

Lesson 5 described N+1, 2N and Tier IV. Those designs protect against a single equipment failure. They do less against:

  • Software and configuration. Automated systems can push a bad change everywhere at once, defeating physical redundancy.
  • Common-mode failures. One cause hits all the redundant parts together: a firmware bug in every UPS, a fuel contamination problem in every generator, a heat wave beyond the cooling design.
  • Maintenance windows. When one side of a 2N system is out for service, the site runs on the other with no spare.
  • Human steps. Switching sequences done in the wrong order.

Worked example: reading a real post-incident report

AWS published a summary of its October 19 to 20, 2025 disruption in the Northern Virginia (us-east-1) Region. Pull out the basics:

  • Start: 11:48 p.m. PDT, October 19
  • Trigger: A latent race condition in DynamoDB's automated DNS management. An older plan overwrote a newer one, and a cleanup process then deleted it, leaving the regional endpoint with no IP addresses.
  • Trigger resolved: DNS records restored by 2:25 a.m. PDT, October 20, with cached entries cleared by 2:40 a.m., about 2 hours 52 minutes after the start
  • Full recovery: 2:20 p.m. PDT, October 20, as knock-on effects in EC2, load balancers and other services cleared
  • Total duration: 11:48 p.m. to 2:20 p.m. is 14 hours 32 minutes

Notice what is missing: no fire, no power failure, no flood. The buildings were fine. A software fault in one service cascaded through others that depended on it. For anyone trying to make sense of it, the useful point is that cloud outages are more often logic failures than physical ones, and that heavy concentration in one region spreads the damage widely.

Grid events and the data center

Reliability runs in both directions. NERC's review of the July 10, 2024 event in the Eastern Interconnection found that about 1,500 MW of data center load switched to backup power after repeated voltage dips, and that about 1,260 MW stayed off the grid for hours. The data centers stayed up. The grid had to manage a sudden drop in demand it had not planned for. As campuses grow toward gigawatts, grid operators treat their behavior during disturbances as a reliability issue in its own right.

Common mix-ups

  • Claim: Big outages are usually caused by hackers. What the evidence shows: Uptime's data points to power, network, software and process failures as the most common causes. Cyber incidents are rising, but most outages are self-inflicted.
  • Claim: More redundancy always means fewer outages. What the evidence shows: Redundancy adds complexity, and complexity creates new ways to fail. Most operators say better procedures would have prevented their last outage.

Reporting angle

  • When a cloud service fails, go to the provider's status page and later its post-incident summary. Quote times and causes from the provider, and say when details are still unconfirmed.
  • Ask local agencies, schools and hospitals which cloud regions their critical systems use and whether they have a fallback.
  • For a local facility, ask the fire marshal and emergency management office about battery storage, fuel storage and response plans. Lithium-ion battery rooms are covered by fire codes such as NFPA 855.
  • Ask the utility whether large data center loads must meet ride-through requirements, and whether any local load loss events have been reported.

Research angle

Pictures, Numbers and Infographics

U.S. data centers tripled their electricity use in ten years, and the federal estimate for 2028 is roughly double to triple the 2023 level. The buildings got more efficient for years, then stalled, as the PUE chart shows.

Long rows of black computer cabinets in a large, brightly lit machine room
The Pleiades supercomputer at NASA Ames Research Center in Mountain View, California, October 2008. Rows of identical cabinets are still the basic layout of a data hall (lesson 4). What has changed most since 2008 is how much power each rack draws, and so how much heat it throws off. Credit: Marco Librero, NASA Ames Research Center. Public domain, via Wikimedia Commons.

By the numbers

U.S. data center electricity use Terawatt-hours per year (2028 is a projected range) 58 2014 176 2023 325 2028 low 580 2028 high
Annual U.S. data center electricity use, with the 2028 low and high projections. Bars drawn to scale. Source: U.S. Department of Energy and Lawrence Berkeley National Laboratory, 2024.
PUE (lower is better; 1.0 would mean zero overhead) Average, 2007 2.50 Average, 2014 1.65 Average, 2025 1.54 Built since about 2020 1.48 20 MW and larger 1.44
Power usage effectiveness is total facility power divided by IT equipment power (lesson 7). Newer and larger sites do better than the industry average. Source: Uptime Institute Global Data Center Survey, 2025.

Check yourself

1. In Uptime Institute's 2026 outage analysis, what was the leading cause of impactful outages in 2025?

2. What share of respondents said their most recent major outage cost more than $100,000?

3. What caused the AWS us-east-1 disruption of October 19 to 20, 2025, according to AWS's own summary?

4. What is a 'mantrap' at a data center entrance?

5. Uptime says 87 percent of respondents with an impactful outage believed it could have been prevented by what?

Terms in this lesson

Mantrap
A secure vestibule with interlocking doors that admits one verified person at a time.
Defense in depth
Layered security, where an intruder must pass several separate barriers to reach the equipment.
Impactful outage
Uptime Institute's term for an outage with significant effects on services, customers or finances.
Post-incident report
A provider's written account of an outage, covering timeline, cause and fixes.
Cascading failure
A failure in one system that triggers failures in others that depend on it.