Lesson 8 of 9 · about 17 minutes
Site Selection, Construction and Jobs
You'll be able to
- List the factors developers use to rank sites and explain why time to power now comes first
- Lay out a typical data center project timeline from land option to operation
- Compare construction employment with permanent employment using sourced figures
- Read a job claim critically and compute cost per job from incentive figures
Developers keep a scorecard for every candidate site. The weights have shifted since 2023. Cheap land and tax breaks used to top the list; now the first question is how many megawatts the site can get and how soon. A perfect parcel that waits seven years for power loses to a mediocre one that can be energized in two.
The site scorecard
| Factor | What developers look for | Why it matters | What to check locally |
|---|---|---|---|
| Power availability and time to power | Hundreds of MW within a few years; nearby high-voltage lines and substations with spare capacity | The single biggest constraint; interconnection waits run years | Utility load forecasts, large load requests, transmission plans |
| Fiber | Two or more long-haul fiber routes from different carriers, on different paths | Redundant connectivity; cloud regions also need low-delay links between zones | Fiber maps from carriers, state broadband office |
| Water | Enough supply for the chosen cooling, or a plan for closed-loop systems | Evaporative cooling needs large volumes on hot days | Water rights, municipal capacity, drought plans |
| Land | Flat, large parcels (hundreds to thousands of acres for AI campuses), zoned or zonable for industrial use | Room for buildings, substations, generators and future phases | Zoning maps, the local land use plan, recent land sales |
| Taxes and incentives | Sales tax exemptions on equipment, property tax abatements | Servers are replaced every few years; sales tax on them adds up fast | State incentive statutes, local abatement agreements |
| Latency | Near users and exchange points (cloud, inference); anywhere with power (training, mining) | Live services feel distance; batch jobs do not | Distance to the nearest major metro and exchange |
| Climate | Cool or dry air for free cooling; low humidity helps evaporative systems | Lower cooling energy and water | Climate normals, cooling degree days |
| Disaster risk | Outside floodplains, away from fault lines, low tornado and wildfire risk | Long-lived, expensive equipment; insurance costs | FEMA flood maps, USGS hazard maps, wildfire risk maps |
| Workforce and politics | Electricians and technicians nearby; a receptive local government | Building and staffing; speed of approvals | Local labor market, past votes on similar projects |
Why power comes first now
CBRE reported in September 2026 that North American primary market vacancy was 1.4 percent and that power constraints were stretching completion timelines. Lawrence Berkeley National Laboratory's 2026 Queued Up report found median waits above five years from interconnection request to commercial operation for generation projects completed in 2025. New load faces its own queue at the utility. Developers respond by buying sites with existing power (old industrial plants, retired coal plant sites, crypto mines), by building their own on-site generation, and by spreading load requests across many utilities and dropping the slow ones.
Concentration has limits. Ireland's Central Statistics Office reported that data centres used 22 percent of the country's metered electricity in 2024, up from 5 percent in 2015. Northern Virginia's 0.2 percent vacancy is a power problem more than a land problem. Those constraints are pushing developers into places that never had a data center before.
A typical timeline
Fast cases exist. At Stargate Abilene, construction began in July 2024 and the first two buildings were reported operational, with more than 200 MW of IT capacity, by September 2025. That speed relied on a site that already had a power plan. Most projects take longer, and big campuses open in phases: one building energized while the next is under construction and a third is a slab.
Jobs: construction versus operation
Data centers create a lot of construction work and relatively few permanent jobs per dollar invested. The ratio is the part people most often get wrong, so whenever a job figure comes up, ask for both numbers.
| Project | Construction workforce | Permanent jobs | Source |
|---|---|---|---|
| Stargate Abilene, Texas (1.2 GW planned) | About 7,000 on site daily, late 2025 | Not stated in the source | Data Center Dynamics |
| Meta Hyperion, Louisiana | More than 3,700, planned to reach 5,000 | 500 announced | Fortune, Feb. 2026 |
| Colocation benchmark | Not applicable | About 20 to 30 per 100 MW | Catherine Curtis, Governing opinion column (no source given for the range) |
Permanent staff include facility engineers, electricians and HVAC technicians, security officers, network and server technicians, and managers. Many work for contractors, not the owner. These jobs often pay well. Hiring them is hard: Uptime Institute's 2025 survey found 46 percent of operators struggle to find qualified candidates and 37 percent struggle to keep staff.
Research on county-level effects is newer. An analysis by Dany Bahar and Greg Wright, published by Brookings in May 2026 and revised in August 2026, compared counties that got large data centers with counties where announced projects were canceled. It found data processing employment up about 56 percent and telecommunications up about 43 percent over the first decade, no change in wages, and home prices up 2 to 5 percent. Industry groups point to broader effects from construction spending and tax revenue. Skeptics point to state reports showing modest job counts against large incentives. Both kinds of evidence are real; they answer different questions.
Worked example: cost per permanent job
Virginia's Department of Taxation, in a 2026 report to the General Assembly (RD40), showed operators reporting 1,610 net new jobs in fiscal 2025 and an aggregate reported tax benefit of about $1.9 billion. Catherine Curtis, a former Southern California Edison employee and planning commissioner, ran the division below in a June 2026 Governing opinion column.
- $1,900,000,000 divided by 1,610 = about $1,180,000 per job
Now an invented local case. The county of Sable Ridge offers a 15-year property tax abatement worth an estimated $240 million on a campus promising 60 permanent jobs.
- $240,000,000 divided by 60 = $4,000,000 per job
- Per year of abatement: $4,000,000 divided by 15 = about $267,000 per job per year
That does not settle whether the deal is good. The campus may still pay more tax than the farmland it replaces, and construction spending is real. But it gives residents and officials a number they can weigh. When you cite it, say which taxes were abated and which still get paid.
Common mix-ups
- Claim: A project that brings 5,000 jobs. What the evidence shows: That is usually peak construction, for a year or two. Ask for permanent jobs separately and whether they are employees or contractors.
- Claim: Data centers go where land is cheapest. What the evidence shows: Land is a small share of total cost. Power, fiber and speed of approval matter far more.
Reporting angle
- Ask for permanent job numbers in writing, with average wages, and whether the incentive agreement has clawbacks if targets are missed.
- Request the incentive or abatement agreement and any performance reports the company must file.
- Check FEMA flood maps for the parcel and note any floodplain overlap.
- Ask the utility for its time-to-power estimate and what upgrades are needed. Check the state transmission plan.
- Compare announced construction workforce with available local trades; ask where workers will live and how traffic will be handled.
Research angle
- CBRE North America data center release: Vacancy, construction and demand figures from a brokerage.
- LBNL Queued Up 2026: Data on projects waiting for a grid connection.
- Brookings on data center jobs: Bahar and Wright on employment effects.
- Virginia report RD40: State report on data center tax benefits.
- Ireland CSO metered data: Official metered electricity use by data centres.
- Uptime Global Survey 2025 report: Rack density, PUE history and staffing findings.
Check yourself
1. In 2026, which factor most often decides where a large data center goes?
With vacancy near record lows and interconnection waits measured in years, time to power has become the top factor.
2. At its peak, the Stargate campus in Abilene, Texas reportedly had about how many construction workers on site daily?
Data Center Dynamics reported about 7,000 electricians, construction workers and other tradespeople coming to the site daily in late 2025.
3. Meta announced how many permanent full-time jobs for its multi-billion-dollar Hyperion campus in Louisiana?
Meta and the state announced 500 permanent positions, compared with a construction workforce of more than 3,700 headed toward 5,000.
4. Virginia's Department of Taxation reported 1,610 new data center jobs in fiscal 2025 while the industry received about $1.9 billion in tax benefits. Roughly what is the cost per job?
$1.9 billion divided by 1,610 jobs is about $1.18 million per job. Catherine Curtis, in a Governing opinion column, rounded it to about $1.2 million.
5. Why does latency matter less for an AI training campus than for a cloud region?
Training runs for weeks inside one cluster, so distance from users barely matters. Live services feel every millisecond.
6. What did the Brookings analysis by Bahar and Wright (updated August 2026) find about wages in counties that got large data centers?
The updated study found gains in data processing and telecom employment but no change in wages, and home prices up 2 to 5 percent.
Terms in this lesson
- Time to power
- How long it will take before a site can get the electricity it needs from the grid or its own generation.
- Powered land
- Land that already has, or has a firm commitment for, a large electric service.
- Entitlement
- The approvals, such as zoning and site plan, that give a landowner the legal right to build a project.
- Shell
- The building structure and envelope, before power and cooling equipment and IT fit-out are installed.
- Fit-out
- Installing the electrical, mechanical and IT systems inside a finished shell.
- Permanent job
- An ongoing position at the operating facility, as opposed to temporary construction work.
Sources
- CBRE: North American data center demand continues to outpace supply despite record construction (Sept. 8, 2026) checked 2026-10
- LBNL: Queued Up, 2026 Edition checked 2026-10
- Data Center Dynamics: Crusoe tops out final building at OpenAI Stargate campus in Abilene, Texas checked 2026-10
- Fortune: Meta expands its already massive Louisiana data center project (Feb. 9, 2026) checked 2026-10
- Brookings: New evidence on data center employment effects (Bahar and Wright, updated Aug. 10, 2026) checked 2026-10
- Governing: The reality of data center jobs (Catherine Curtis, opinion, June 24, 2026) checked 2026-10
- Virginia General Assembly report RD40 (2026), data center tax benefits checked 2026-10
- Uptime Institute Global Data Center Survey 2025 (staffing findings) checked 2026-10
- CSO Ireland: Data Centres Metered Electricity Consumption 2024 checked 2026-10