Lesson 7 of 9 · about 20 minutes
What Energy Costs: LCOE, System Costs and Tax Credits
You'll be able to
- Calculate a simple LCOE from capital cost, financing, operating cost and capacity factor
- Read Lazard's and EIA's 2026 cost tables and explain why they differ
- Explain what LCOE leaves out (timing, firming, transmission, curtailment) and what EIA's value-cost ratio adds
- State the 2025 federal tax law's main deadlines for wind, solar, storage, geothermal, nuclear, hydrogen and rooftop credits
Ask which power source is cheapest and you will usually get a number in dollars per megawatt-hour. That number is almost always a levelized cost of energy, or LCOE. It is useful. It is also the most misused figure in energy debates. Once you can build one yourself, you will know exactly what it hides.
What LCOE is
LCOE asks: what constant price per MWh, charged over a plant's whole life, would exactly pay back everything it cost, including a fair return to the people who financed it? Put simply:
LCOE = (annualized capital cost + yearly fixed O&M) / yearly MWh
+ variable O&M per MWh + fuel per MWh
The "annualized capital cost" comes from a capital recovery factor (CRF), which turns a lump sum into equal annual payments, the same math as a mortgage.
CRF = r x (1 + r)^n / ((1 + r)^n - 1)
r = discount rate (the cost of capital), n = years
At 7% over 30 years: CRF = 0.0806
Worked example: build an LCOE
Solar on Mesa Verde Flats (invented)
A developer plans a 100-MW (AC) solar plant.
Capital cost: $150 million ($1,500 per kW)
Fixed O&M: $2 million per year
Fuel: $0
Capacity factor: 25%
Life and rate: 30 years at 7%
Step 1, annual capital charge: $150,000,000 x 0.0806 = $12,090,000
Step 2, total annual cost: $12,090,000 + $2,000,000 = $14,090,000
Step 3, annual output: 100 MW x 8,760 h x 0.25 = 219,000 MWh
Step 4, LCOE: $14,090,000 / 219,000 = $64.3 per MWh
Now change one input at a time:
| Change | New LCOE | Why |
|---|---|---|
| Capacity factor 18% instead of 25% | $89.4 | Same cost, 28% fewer MWh |
| Cost of capital 10% instead of 7% (CRF 0.1061) | $81.8 | Capital is most of the cost, so financing matters a lot |
| Capital cost $1,200/kW instead of $1,500 | $53.3 | Cheaper panels and labor |
Gas combined cycle in Harlan County (invented)
500 MW, $700 million capital, $7.5 million fixed O&M, 60% capacity factor
Heat rate 6,500 Btu/kWh = 6.5 MMBtu per MWh, gas at $3.48/MMBtu
(EIA's October 2026 forecast of the 2026 Henry Hub average)
Variable O&M $3/MWh
Annual capital charge: $700,000,000 x 0.0806 = $56,420,000
Fixed costs per MWh: ($56.42M + $7.5M) / (500 x 8,760 x 0.60 = 2,628,000 MWh) = $24.3
Fuel per MWh: 6.5 x $3.48 = $22.6
Total LCOE: $24.3 + $22.6 + $3.0 = about $49.9 per MWh
Same plant run at 30%: fixed costs double per MWh, LCOE = about $74.3
A gas plant's LCOE depends on how much it runs, which depends on how much wind and solar the grid has. And fuel price swings move its cost; double gas to $6.96 and fuel alone becomes $45.24 per MWh.
The 2026 estimates
Lazard, 2026 LCOE+ (version 19.0), unsubsidized, $ per MWh
| Technology | Low | High |
|---|---|---|
| Wind, onshore | $37 | $99 |
| Solar PV, utility | $40 | $98 |
| Wind plus storage | $49 | $140 |
| Gas combined cycle | $51 | $129 |
| Solar plus storage | $61 | $156 |
| Geothermal | $67 | $111 |
| Coal | $72 | $177 |
| Wind, offshore | $105 | $167 |
| Gas peaking | $144 | $276 |
| U.S. nuclear (based on Vogtle 3 and 4) | $175 | $255 |
Lazard assumed 60 percent debt at 8 percent and 40 percent equity at 12 percent, gas at $3.45/MMBtu, and capacity factors of 20 to 30 percent for utility solar and 30 to 55 percent for onshore wind (an after-tax WACC of about 7.7 percent). It said renewables remained the lowest-cost new-build generation but that wind and solar costs rose again, and that gas combined cycle costs hit a 15-year high with turbine supply constrained. With the production tax credit, the low end of Lazard's range drops to about $16 for utility solar and $11 for onshore wind.
EIA, Annual Energy Outlook 2026, plants entering service in 2031, 2025 dollars per MWh
| Plant type | Capacity factor | LCOE before tax credit | With tax credit |
|---|---|---|---|
| Geothermal | 90% | $48.69 | $40.38 |
| Wind, onshore | 38% | $56.75 | $56.75 (no credit) |
| Solar, standalone | 27% | $58.33 | $58.33 (no credit) |
| Combined cycle gas | 40% | $77.46 | n/a |
| Hydroelectric | 56% | $82.08 | $64.77 |
| Advanced nuclear | 90% | $110.87 | $87.81 |
| Wind, offshore | 43% | $118.79 | $118.79 |
| Combustion turbine | 10% | $172.57 | n/a |
| Battery storage (LCOS) | 10% | $190.45 | $152.61 |
EIA used a 30-year recovery period and a 7.27 percent after-tax cost of capital, and included only laws in effect as of December 2025. Because EIA's 2031 wind and solar plants miss the new credit deadlines, they get no credit in its table. Note EIA's 40 percent capacity factor for the gas plant: EIA's baseline models the EPA's April 2024 Section 111 rule, which caps new combined-cycle plants without carbon capture at about 40 percent. In EIA's Alternative Electricity case, which assumes that rule is repealed, the plant runs at 87 percent and its LCOE falls to $55.51.
What LCOE leaves out
LCOE treats every MWh as equal. The grid does not.
- Timing: A MWh at 7 p.m. in August can be worth ten times a MWh at noon in April. Solar's output is concentrated in hours whose price falls as more solar is built.
- Firming and reliability: A variable plant needs backup capacity for its low-output hours. Lazard's 2026 firming analysis added roughly $8 to $36 per MWh for wind and for wind and solar storage hybrids across the six grid operators it studied, highest in ERCOT, with standalone solar higher still in some markets. Gas plants have their own reliability costs (fuel supply, pipeline limits, winter outages) that Lazard says it did not model.
- Transmission and interconnection: EIA includes a levelized transmission charge of only a few dollars per MWh; remote wind can need hundreds of miles of new lines.
- Curtailment: If 10 percent of output gets curtailed, the effective cost of the energy actually used rises about 11 percent.
- Emissions and health costs: Not included unless a carbon price is modeled. In Lazard's carbon price sensitivity, the gas combined cycle range moves from $51 to $129 up to $59 to $152.
EIA's answer is to compare LCOE with LACE, the levelized avoided cost, an estimate of what the plant's output is worth in its region and hours. If LACE is higher than LCOE, the plant pays for itself. EIA says this value-cost ratio is more useful than either number alone. In EIA's 2026 regional data, standalone solar in one region showed an LCOE of $78.59 and a LACE of $63.49, a sign it would not pay there without other support.
Subsidies and the 2025 tax law
Every energy source has had federal help: depletion allowances and drilling expense deductions for oil and gas, loan guarantees and liability caps for nuclear, and tax credits for wind and solar. The Inflation Reduction Act of 2022 created technology-neutral credits, section 45Y (per MWh) and 48E (share of investment). The 2025 tax law, Public Law 119-21, often called the One Big Beautiful Bill Act, rewrote them:
| Credit | Change under Public Law 119-21 |
|---|---|
| 45Y / 48E for wind and solar | No credit for facilities that begin construction after July 4, 2026 and are placed in service after December 31, 2027 |
| 45Y / 48E for storage, geothermal, hydro, nuclear | Remain eligible for projects beginning construction through 2033, then phase down for later construction starts |
| 25D residential clean energy (rooftop solar, home batteries) | Ended for expenditures after December 31, 2025 |
| 45V clean hydrogen | Facilities must begin construction before January 1, 2028 (was 2033) |
| 45X manufacturing, wind components | Wind components sold after 2027 no longer qualify |
| Foreign entity of concern rules | New limits on Chinese-linked ownership and components, generally for tax years beginning after July 4, 2025 |
"Begin construction" is its own fight. IRS Notice 2025-42 (August 15, 2025) eliminated the 5 percent cost safe harbor for most wind and solar, leaving a "physical work" test. On June 6, 2026, the U.S. District Court for the District of Columbia vacated that notice in Oregon Environmental Council v. IRS, finding it arbitrary and capricious, which restored older guidance for now. Tax practitioners expected an appeal. If you are following a local project's credit status after July 2026, ask which guidance its developer relied on and get the current status of that case.
Supporters of the cuts argued the credits cost far more than originally scored and subsidized mature technologies. Opponents argued they would raise power prices and slow new supply just as demand from data centers climbs. Both claims are testable; watch EIA's planned capacity data and utility rate cases over the next few years.
Common mix-ups
- Claim: The lowest LCOE is always the cheapest choice for a grid. What the evidence shows: LCOE ignores timing, firming, transmission and curtailment. EIA pairs it with LACE for that reason.
- Claim: Solar is cheap only because of subsidies. What the evidence shows: Lazard's unsubsidized 2026 solar range ($40 to $98) overlaps and undercuts new gas combined cycle ($51 to $129). Subsidies lower it further.
- Claim: All federal clean energy credits were repealed in 2025. What the evidence shows: Wind, solar and residential credits were cut sharply. Storage, geothermal, hydro and nuclear kept credits through 2033 construction starts.
Reporting angle
- When a utility or developer cites an LCOE, ask for the capacity factor, cost of capital, capital cost, life and fuel price behind it. Rebuild it with the formula.
- Ask what tax credit the project assumes, its construction start date and placed-in-service target.
- In a utility rate case or resource plan, find the "levelized cost" tables and the capacity value assigned to each resource.
- Ask local officials whether state or county tax breaks apply (property tax abatements, sales tax exemptions) and what they total.
Research angle
- Lazard LCOE+ full report: Cost ranges and assumptions behind each figure.
- EIA levelized costs, AEO2026: Federal cost projections with figure data.
- EIA Short-Term Energy Outlook, natural gas: Current gas price forecasts.
- Stoel Rives on the beginning of construction ruling: Court action on tax credit guidance.
- RSM summary of federal clean energy credit changes: Which credits end and when.
Check yourself
1. What does a capital recovery factor do in an LCOE calculation?
It converts the up-front cost into a level annual charge over the plant's life at a given interest or discount rate.
2. In the module's worked example, a 100-MW solar plant at a 25 percent capacity factor costs about $64/MWh. What happens to its LCOE at an 18 percent capacity factor with the same costs?
Same annual cost divided by fewer MWh: 64 x 25 / 18 is about 89.
3. What is Lazard's 2026 unsubsidized LCOE range for utility-scale solar PV?
Lazard v19.0 lists $40 to $98 unsubsidized. The production tax credit pulls the low end down to about $16.
4. Under Public Law 119-21 (the 2025 tax law), wind and solar facilities that begin construction after July 4, 2026 must be placed in service by when to keep the 45Y or 48E credit?
The law cuts off wind and solar credits for facilities that start construction after July 4, 2026 and are placed in service after December 31, 2027.
5. Why does EIA say comparing LACE to LCOE is more useful than LCOE alone?
LCOE is cost per MWh. LACE estimates the value of those MWh given when and where they are produced. Their ratio tells you if a plant is worth building.
6. Under the 2025 law, which of these keeps access to the technology-neutral credits for projects that begin construction through 2033?
Storage, geothermal, hydro and nuclear remain eligible for construction starting through 2033. 25D ended after 2025, and 45V requires construction to start before 2028.
Terms in this lesson
- LCOE (levelized cost of energy)
- The constant price per MWh that would recover a plant's capital, financing, operating and fuel costs over its life.
- Capital recovery factor
- The share of an upfront cost to charge each year so the investment is repaid with interest over a set life.
- WACC
- Weighted average cost of capital: the blended return lenders and owners require, which acts as the discount rate in LCOE.
- LACE
- Levelized avoided cost of electricity: EIA's estimate of the value of a new plant's output, based on what it would displace.
- PTC and ITC
- Production tax credit (per MWh generated) and investment tax credit (a share of project cost). Now sections 45Y and 48E.
- Beginning of construction
- The IRS test for when a project counts as started, which decides which tax credit rules apply.
Sources
- Lazard, 2026 Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), full report PDF checked 2026-10
- EIA, Levelized Costs of New Generation Resources in the Annual Energy Outlook 2026 (report and figure data) checked 2026-10
- Orrick, IRS Issues Guidance on Beginning of Construction for Wind and Solar Facilities Under the OBBBA (Aug. 2025) checked 2026-10
- Stoel Rives, District Court Vacates IRS Beginning of Construction Notice (June 10, 2026) checked 2026-10
- RSM, Tax bill significantly changes clean energy credits and incentives checked 2026-10
- Clifford Chance, One Big Beautiful Bill Act: notable terminations of tax credits for solar, wind, hydrogen and clean vehicles (Nov. 2025) checked 2026-10
- EIA Short-Term Energy Outlook, Natural gas (October 6, 2026) checked 2026-10
- EIA Today in Energy, record capacity additions planned for 2026 (Feb. 20, 2026) checked 2026-10