Lesson 8 of 8 · about 18 minutes
Reliability and the Grid's Future
You'll be able to
- Explain the main causes of large blackouts using real investigation findings
- Summarize NERC's 2025 Long-Term Reliability Assessment, including the Northwest outlook
- Read an integrated resource plan and find the load forecast, resource choices and assumptions worth questioning
Grid reliability gets attention for about three days after a blackout and then disappears until the next one. The decisions that cause or prevent the next one are made years earlier, in resource plans, transmission studies and rate cases that almost nobody outside the industry follows. That gap is where an engaged resident or advocate can do the most good.
Why the lights go out
Blackouts split into local and wide-area events. Local outages, the common kind, come from the distribution system: a tree on a line, a car into a pole, a failed transformer, a storm. Wide-area events come from the bulk system, either a cascade of failures or a shortage of supply that forces operators to shed load on purpose.
| Event | What happened | Main causes found by investigators |
|---|---|---|
| August 14, 2003, Northeast and Midwest U.S. and Ontario | About 50 million people and 61,800 MW of load lost power, some for up to four days | Transmission lines in Ohio sagged into untrimmed trees; the utility did not see its system deteriorating; monitoring tools failed. The task force said it could have been prevented. |
| February 2021, Winter Storm Uri, mostly Texas | ERCOT ordered 20,000 MW of rotating outages; more than 4.5 million people in Texas lost power, some for up to four days | Freezing equipment (44.2% of unplanned outages) and fuel supply problems (31.4%), most involving natural gas. About 81% of freeze-related outages happened at temperatures above the units' stated design limits. |
| December 2022, Winter Storm Elliott, Eastern Interconnection | About 90,500 MW of generation out at the worst point; 5,400 MW of firm load shed | Mechanical and electrical failures (41%), freezing (31%) and fuel issues (24%). Gas units were 47% of affected units, wind 21%, coal 12%. |
Look at the winter storm rows together, because they cut against the claims of every side in the energy argument. Gas plants failed in the largest numbers, and gas fuel supply froze up. Wind turbines froze too. Coal piles froze. Nuclear units were less than 1 percent of affected units in both storms, though one Texas reactor did trip during Uri. The common failure was cold-weather preparation across almost every fuel type, and the main fixes were winterization standards, gas and electric coordination, and better planning for extreme cold. NERC has since strengthened its cold weather reliability standards.
Extreme weather is the main stressor
Heat waves push summer peaks past forecasts. Cold snaps hit gas supply and raise heating load at the same time. Drought cuts hydro, which matters a lot in the Northwest: lower forecast hydro was the main driver of Idaho Power's 2026 power cost increase. Wildfire is its own category in the West, where utilities now plan public safety power shutoffs in high-risk conditions.
What NERC says about the next ten years
NERC's 2025 Long-Term Reliability Assessment, released January 29, 2026, was its starkest yet. Trade press coverage of the LTRA gives these top-line numbers:
- Summer peak demand projected to grow about 224 GW over 10 years, 69 percent more growth than the prior year's forecast. Winter peak growth about 245 GW. NERC called the growth rates the highest since its tracking began in 1995.
- 13 of 23 assessment areas carry an above-normal or high risk rating for resource shortfalls over the next five years.
- Data centers are the main driver of new load in many areas, with large industrial loads and electrification adding more.
- WECC-Northwest: peak load up about 6.6 GW (19 percent), much of it from data centers; risk normal for 2026 to 2028 and high beginning in 2029, with winter peaks and reliance on variable resources named as concerns. NERC also named WECC-Basin, along with MISO, PJM and ERCOT, among areas that could reach high risk by 2030.
A forecast is not a fact. NERC's numbers aggregate what utilities report, and utilities' large-load forecasts include many projects that may never be built or may be counted by more than one utility as developers shop for sites. Whether the forecasts are inflated is a real dispute. Some analysts and consumer advocates argue utilities have an incentive to overbuild against speculative load. Utilities and grid operators answer that the signed contracts and requests for service are real and that underbuilding risks blackouts. Both are reasonable concerns. The way to judge your own utility is to ask how much of its forecast is under signed agreement and how much is "pipeline."
The scale of data center demand
The Department of Energy's report estimated data centers used 176 TWh in 2023, about 4.4 percent of U.S. electricity, and projected 6.7 to 12 percent by 2028. The width of that range is the honest answer. Module 18, on data centers, covers how these facilities use power, and module 19 covers their local impacts.
The bottlenecks: wires and queues
Building generation is often faster than connecting it. Lawrence Berkeley National Laboratory's Queued Up report (2026 edition, data through 2025) counted over 2,060 GW of generation and storage seeking grid connection, more than the whole existing U.S. fleet of about 1,281 GW. Of capacity that requested connection from 2000 to 2020, only 13 percent was operating by the end of 2025; about 75 percent withdrew. Projects built in 2025 had a median wait of more than five years from request to operation.
Transmission is slower still. A major line can take a decade or more from proposal to energizing, crossing federal land, private land and multiple states. FERC's Order No. 1920 (2024) now requires transmission providers to plan at least 20 years ahead and update every five years. In Idaho, the Boardman to Hemingway 500 kV line between Oregon and southwest Idaho has been in development for close to two decades; Idaho Power's 2025 plan targets service by the end of 2027.
Reading an integrated resource plan
Most vertically integrated utilities must file an IRP every two years or so: a 20-year forecast of demand and a "preferred portfolio" of resources to meet it. In Idaho the PUC "acknowledges" a plan rather than approving it. Acknowledgment means the commission found the plan a reasonable working document. It does not pre-approve the costs; each investment still has to pass a prudence review in a later rate case.
Real plan: Idaho Power's 2025 IRP (IPC-E-25-23)
Filed June 27, 2025 and acknowledged by the Idaho PUC on February 17, 2026 in Order No. 36937. Highlights from the commission's release and press coverage:
- Peak demand up about 1,700 MW over 20 years, with about 1,000 MW in the first five years.
- Customers growing from about 648,000 to about 867,000 by 2045.
- Preferred portfolio: 1,445 MW solar, 885 MW batteries, 700 MW wind, 611 MW of coal units converted to gas, 550 MW new gas, 344 MW energy efficiency, 20 MW added demand response.
- Transmission in the preferred portfolio: SWIP-N online November 2028 and Boardman to Hemingway in December 2027. The 2023 IRP had left SWIP-N out because Idaho Power's involvement was "uncertain" (acknowledged in Order No. 36233, June 18, 2024). Pierson's Point by Point Rebuttal turns on that change.
- Large-load growth cited from a major data center and a semiconductor expansion in the Boise area.
Quick check on scale: 1,000 MW of new peak in five years against the utility's existing peak (look up its record peak in the IRP) shows how big a jump that is. If the record peak were about 3,700 MW, 1,000 MW would be a 27 percent increase in five years, 1,000 / 3,700 = 0.27. Verify the actual peak in the plan before you repeat a percentage.
Where to look in any IRP
- Load forecast. Find base, high and low cases. How much comes from large loads, and how many of those have signed agreements? What assumptions about electric vehicles and heat pumps are built in?
- Existing resources and retirements. Which plants retire or convert, and when? What happens to coal contracts?
- Resource accreditation. The table assigning capacity credit to each resource type (lesson 4). Small changes here swing the whole portfolio.
- Cost assumptions. Gas price forecast, cost of solar, wind and batteries, carbon cost assumptions if any. Compare to the last plan.
- Market and transmission assumptions. How much does the plan count on importing power, or on a line that is not built yet?
- Preferred portfolio vs. alternatives. IRPs usually test several portfolios. Find the cost difference between the preferred one and the runners-up, and the reasons given.
- Action plan. The near-term list, often the next two to four years, is what the utility will actually build or buy first. It turns into requests for proposals and later into rate cases.
- Comments. Read staff and intervenor comments in the IRP docket. They point at the weakest assumptions.
Common mix-ups
- Claim: "Renewables caused the Texas blackout." What the evidence shows: FERC and NERC found gas units made up 58 percent of unplanned outages, derates and failures to start, wind 27 percent, coal 6 percent. Freezing and gas supply problems drove most of it.
- Claim: "Fossil plants are always there when needed." What the evidence shows: In Uri and Elliott, gas and coal units failed in large numbers in extreme cold. Every resource type has conditions under which it fails, which is why planners discount all of them.
- Claim: "A project in the interconnection queue is coming." What the evidence shows: Historically about three in four queued megawatts withdrew. Treat queue entries as proposals.
- Claim: "The commission approved the utility's plan to build these plants." What the evidence shows: In Idaho, acknowledging an IRP does not approve any plant for rates. That comes later, project by project.
Reporting angle: reading an IRP and a rate case docket
- Find the docket. Each IRP and rate case has a commission case number. Idaho Power's 2025 IRP is IPC-E-25-23; its 2025 rate case is IPC-E-25-16. Bookmark the case page and check it weekly.
- Connect plan to rates. Items in an IRP action plan show up two to five years later in rate cases. Keep a list and follow each one forward: projected cost in the plan versus actual cost requested.
- Ask for the large-load list. Utilities may treat named customers as confidential, but the number of requests, total MW, and how many have signed agreements are often public or obtainable through production requests.
- Watch the NERC and WECC assessments. NERC publishes summer and winter assessments each year plus the long-term one. Compare your area's risk rating to your utility's own reserve margin.
- Numbers to check: record peak and year, reserve margin, MW of large-load requests, MW under signed contracts, the gas price assumption, and the projected residential bill impact of the preferred portfolio.
Research angle
- FERC, February 2021 freeze final report: Findings and winterization recommendations.
- DOE final report on the 2003 blackout: Causes and recommendations from the joint task force.
- LBNL Queued Up: Interconnection queue data by region and resource type.
- FERC Order No. 1920 fact sheet: Regional transmission planning and cost allocation rules.
- DOE report on data center demand: Federal load growth estimates.
- Idaho Public Utilities Commission: Integrated resource plan reviews and orders.
Pictures, Numbers and Infographics
The U.S. grid runs mostly on natural gas, then nuclear and coal, with wind, hydro and solar making up most of the rest. Idaho's in-state mix leans on hydro, and its average price and its carbon dioxide per megawatt-hour both run well below the national figures.
By the numbers
- 4,178 billion kWh: electricity generated at U.S. utility-scale plants in 2023. Natural gas supplied 43.1%, nuclear 18.6% and coal 16.2%. U.S. Energy Information Administration, 2024
- 1,230,416 megawatts: U.S. net summer generating capacity in 2024. Idaho's was 5,548 megawatts. EIA, United States Electricity Profile 2024
- About 5%: average share of electricity lost in U.S. transmission and distribution lines, 2018 through 2022. EIA, 2023
- 11 hours: average time a U.S. electricity customer went without power in 2024, nearly twice the annual average of the decade before. Hurricanes Beryl, Helene and Milton and other major events accounted for 80% of it. EIA, Today in Energy, 2025
- 12.94 cents per kWh: average U.S. retail electricity price, all sectors, in 2024. Idaho's average was 9.51 cents, 44th in EIA's state ranking. EIA, Idaho Electricity Profile 2024
- 382 pounds: carbon dioxide per megawatt-hour generated in Idaho in 2024, against a U.S. figure of 785. Hydroelectric is Idaho's primary energy source. EIA, Idaho Electricity Profile 2024
Check yourself
1. According to the FERC and NERC report on February 2021's Winter Storm Uri, what were the two largest causes of unplanned generator outages?
Freezing issues (44.2 percent) and fuel issues (31.4 percent) together caused about 76 percent of unplanned outages, with most fuel issues involving natural gas.
2. What started the August 14, 2003 blackout that affected about 50 million people?
The U.S.-Canada task force found inadequate tree trimming, an operator who did not see the system deteriorating and weak real-time diagnostic support. It concluded the blackout could have been prevented.
3. NERC's 2025 Long-Term Reliability Assessment projected summer peak demand growth over the next 10 years of about how much?
NERC projected about 224 GW of summer peak growth over 10 years, 69 percent above the previous year's forecast, driven largely by data centers.
4. What did NERC's 2025 assessment say about the WECC-Northwest area?
As reported from the LTRA, WECC-Northwest shifts to high risk beginning in 2029, with peak load rising about 6.6 GW, much of it from data centers.
5. What does it mean when the Idaho PUC 'acknowledges' an integrated resource plan?
An IRP is a planning document. Acknowledgment says the process and plan were reasonable at the time. Specific investments are still reviewed for prudence when the utility asks to put them in rates.
6. By the end of 2025, according to LBNL's Queued Up report, how much generation and storage capacity was waiting in U.S. interconnection queues?
LBNL's 2026 edition counted over 2,060 GW of generation and storage seeking connection, more than the entire existing U.S. fleet, though most queued projects historically never get built.
Terms in this lesson
- Load shed
- Deliberately cutting power to some customers, often in rotating blocks, to keep the wider grid from collapsing.
- Resource adequacy
- Having enough supply, including reserves, to meet demand across all hours and conditions the planners expect.
- Integrated resource plan (IRP)
- A utility's long-term plan, often 20 years, forecasting demand and choosing the mix of resources to meet it.
- Interconnection queue
- The line of proposed generation and storage projects waiting for studies and approval to connect to the grid.
- Large load
- A single new customer, such as a data center or factory, big enough to change a utility's forecast, often tens to hundreds of MW.
Sources
- U.S. DOE: Final report on the August 14, 2003 blackout in the United States and Canada checked 2026-10
- FERC: Final report on February 2021 freeze underscores winterization recommendations checked 2026-10
- Power Engineering: FERC-NERC final report, natural gas struggled the most during Winter Storm Elliott checked 2026-10
- POWER Magazine: NERC warns long-term grid reliability risks mounting from surging demand, lagging resources (2025 LTRA) checked 2026-10
- Power Engineering: NERC warns reliability risk is rising as load growth outpaces infrastructure checked 2026-10
- U.S. DOE: DOE releases new report evaluating increase in electricity demand from data centers checked 2026-10
- Lawrence Berkeley National Laboratory: Queued Up (2026 edition) checked 2026-10
- FERC fact sheet: Order No. 1920, regional transmission planning and cost allocation checked 2026-10
- Idaho PUC news release: Commission acknowledges Idaho Power 2025 IRP (Feb. 18, 2026) checked 2026-10
- Idaho Capital Sun: Idaho Power's 20-year energy plan predicts large increase in customer growth and peak energy load checked 2026-10
- Idaho PUC Order No. 36233, acknowledging the 2023 IRP (June 18, 2024) checked 2026-10
- Idaho PUC Order No. 36937, acknowledging the 2025 IRP (Feb. 17, 2026) checked 2026-10