Lesson 6 of 8 · about 16 minutes
Who Regulates the Grid
You'll be able to
- Assign a given grid decision to FERC, NERC, a state commission or a local board
- Explain the revenue requirement formula behind a rate case
- Follow the steps of a rate case and know where the public can take part
Three layers of regulators touch every kilowatt-hour, and each one has a fence around what it can decide. People lose hours calling the wrong agency. The fastest test: ask whether the question is about wholesale and high-voltage (federal), reliability rules for the bulk grid (NERC), or what a retail customer pays and how the local utility behaves (state or local).
The layers
FERC
The Federal Energy Regulatory Commission is an independent agency of five commissioners. It regulates the transmission and wholesale sale of electricity in interstate commerce, approves the tariffs that run markets like the WEIM, EDAM and Markets+, licenses non-federal hydro dams, approves NERC's reliability standards and polices market manipulation. Its 2024 Order No. 1920 requires transmission providers to plan regionally at least 20 years out.
FERC's own page is blunt about what it does not do: it does not regulate retail electricity sales to consumers, approve construction of power plants, or regulate municipal utilities, federal power marketing agencies and most rural co-ops. A customer angry about their bill almost never has a FERC problem.
NERC and WECC
The North American Electric Reliability Corporation is a nonprofit that FERC certified as the Electric Reliability Organization after the Energy Policy Act of 2005 made reliability standards mandatory. NERC writes standards on things like cold-weather preparation, vegetation near transmission lines and cybersecurity. FERC approves them. NERC and six regional entities audit utilities and can levy fines. In the West, the regional entity is WECC. NERC also publishes the seasonal and long-term reliability assessments covered in lesson 8.
State commissions
The Idaho Public Utilities Commission has three commissioners appointed by the governor and confirmed by the Senate, with no more than two from the same party, serving staggered six-year terms. It regulates investor-owned utilities such as Idaho Power, Avista, Rocky Mountain Power (PacifiCorp) and Intermountain Gas. It does not regulate co-ops or city utilities. Its staff, a team of engineers, accountants and attorneys, is a party in every case and often the most informed skeptic in the room.
| Decision | Who decides (for an Idaho IOU) |
|---|---|
| Residential rate per kWh | Idaho PUC |
| Price a utility pays for wholesale power from another state | Negotiated, under FERC rules |
| Whether a new gas plant is prudent and can go in rates | Idaho PUC |
| Cold-weather standards for generators | NERC, approved by FERC |
| Cost to move power on an interstate transmission line | FERC (open access transmission tariff) |
| A city utility's rates | City council or utility board |
| Joining EDAM or Markets+ | The utility decides, with FERC approving tariffs and state commissions reviewing the costs |
How a rate case works
A regulated utility gets a deal: a monopoly on its territory in exchange for letting the state set its prices. The price is supposed to cover reasonable costs plus a fair return for investors, no more. A rate case is how the commission works out that number.
The formula
Revenue requirement = Operating expenses
+ Depreciation
+ Taxes
+ (Rate base x Rate of return)
Rate base is the net value of plants, lines and equipment serving customers. The rate of return blends the interest rate on the utility's debt with an allowed return on equity for shareholders. Because profit comes from rate base, an investor-owned utility earns more by building more, which is why regulators test whether each investment was prudent and "used and useful." That incentive is built into the system on purpose, and anyone weighing in on a rate case should understand it first.
Example: a simplified revenue requirement
Invented Basin River Electric files a case.
Operating expenses (fuel, payroll, maintenance): $420 million
Depreciation: $110 million
Taxes: $45 million
Rate base: $3,000 million
Rate of return (blended debt and equity): 7.2%
Return = $3,000M x 0.072 = $216 million
Revenue requirement = 420 + 110 + 45 + 216 = $791 million
Current rates bring in $730 million.
Requested increase: 791 - 730 = $61 million, or 61 / 730 = 8.4%
Now watch the fights. Staff argues return on equity should be lower, cutting the rate of return to 7.0 percent: 3,000 x 0.070 = $210 million, saving $6 million. An industrial group argues $150 million of a new substation is not yet used and useful and should come out of rate base: 150 x 0.072 = $10.8 million less return, plus that asset's depreciation. Each adjustment is small. Stack a dozen and the request shrinks fast, which is what usually happens.
The steps
- Filing. The utility files an application, testimony from its experts and proposed new tariffs. Idaho Code 61-307 requires 30 days' notice to the commission and public before rates change, unless the commission allows otherwise for good cause.
- Suspension and notice. The commission usually suspends the proposed rates while it reviews them. Under Idaho Code 61-622 the initial suspension is up to 30 days, extendable by up to five months, plus 60 more days for good cause. It issues a notice of application with deadlines.
- Intervention. Groups such as large industrial customers, irrigators, consumer advocates and environmental groups petition to become intervenors.
- Discovery. Parties send written questions (production requests) and the utility must answer. The answers are often the richest public record in the case.
- Testimony. Staff and intervenors file their own expert testimony proposing different numbers.
- Settlement or hearing. Many cases settle, with some or all parties agreeing to a number. The commission still has to approve it and can reject it.
- Public comment and hearings. Customers can file written comments and speak at public hearings. These are part of the record.
- Final order. The commission issues a written order with its reasons. Parties can ask for reconsideration and then appeal.
Real case: Idaho Power, IPC-E-25-16
Idaho Power asked the Idaho PUC in 2025 for a $199.1 million increase. The commission approved a settlement for $110 million a year, a 7.48 percent overall increase, effective January 1, 2026. It estimated a residential customer using 900 kWh a month would pay about $12.13 more per month and kept the residential service charge at $15.00. The company got about 55 percent of what it asked for (110 / 199.1 = 0.55), a common kind of outcome.
Common mix-ups
- Claim: "The commission rubber-stamps whatever the utility wants." What the evidence shows: Outcomes vary, but approved increases are often well below the request, as in IPC-E-25-16. The fair test for any one case is to compare the request, the staff position and the final order line by line.
- Claim: "Utility profits are whatever they can squeeze out." What the evidence shows: Investor-owned utility returns are set as an allowed return on equity in rate cases. Utilities can over- or under-earn between cases, and the earnings reports filed with commissions show which.
Reporting angle: reading a rate case docket
- Every Idaho PUC case has a number like IPC-E-25-16: utility code, industry (E for electric), year, sequence. Search the commission's case files by that number.
- Read in this order: the notice of application (plain-language summary and deadlines), the utility's application, staff's comments or testimony, any settlement, then the final order.
- Find the requested return on equity and the approved one. Find the biggest disputed rate base items. Those are your story.
- Read the production requests and responses. Questions from staff often point straight at the weakest part of the utility's case.
- Read public comments. They are public records and can lead you to customers with specific stories.
- Note the comment deadline and hearing dates and publish them early, so readers can take part.
Research angle
- FERC, what FERC does: Federal authority over wholesale power and transmission.
- NERC, about NERC: The reliability standards body and its role.
- Idaho Public Utilities Commission: Cases, orders and comment procedures.
- Idaho Code 61-622: Rate changes and suspension.
- Idaho Code 61-307: Notice requirements for rate increases.
Check yourself
1. Which agency regulates retail electricity rates for an investor-owned utility in Idaho?
FERC states that retail electricity sales to consumers are outside its authority. State commissions such as the Idaho PUC set retail rates for investor-owned utilities.
2. What does NERC do?
NERC is the Electric Reliability Organization. It writes reliability standards, FERC approves them, and NERC and six regional entities enforce them.
3. In the revenue requirement formula, what is 'rate base'?
Rate base is the depreciated value of investment serving customers. The utility earns its authorized return on it, which is why what goes into rate base is fought over.
4. In Idaho Power's 2025 general rate case (IPC-E-25-16), the company asked for $199.1 million. What did the commission approve?
The commission approved a settlement for $110 million annually, effective January 1, 2026, which it estimated at about $12.13 a month for a residential customer using 900 kWh.
5. Under Idaho law, how long can the commission suspend a proposed rate schedule while it reviews it?
Idaho Code 61-622 allows an initial suspension of up to 30 days, an extension of up to five months, and an additional 60 days for good cause.
Terms in this lesson
- FERC
- The Federal Energy Regulatory Commission, which regulates interstate transmission and wholesale electricity sales.
- NERC
- The North American Electric Reliability Corporation, the federally certified body that writes and enforces reliability standards for the bulk grid.
- Public utility commission (PUC)
- The state agency that sets retail rates and service rules for investor-owned utilities.
- Rate case
- A formal proceeding in which a utility asks regulators to change its rates and must justify the costs.
- Revenue requirement
- The total money a utility is allowed to collect in a year: operating costs plus depreciation, taxes and a return on rate base.
- Intervenor
- A party formally admitted to a regulatory case, with the right to file testimony, ask questions and sign or oppose settlements.
Sources
- FERC: What FERC does checked 2026-10
- NERC: About NERC checked 2026-10
- Idaho Public Utilities Commission: About the Commission checked 2026-10
- Idaho Code 61-622: Changes in rates, suspension checked 2026-10
- Idaho Code 61-307: Increases in rates, notice checked 2026-10
- Idaho PUC news release: Commission approves Idaho Power settlement (Dec. 30, 2025) checked 2026-10
- Idaho PUC: Notice of Application, Order No. 36638, Case IPC-E-25-16 checked 2026-10