Lesson 5 of 10 · about 30 minutes
How the Forest Service Plans: Forest Plans, Projects, Objections and the 2026 Restructure
You'll be able to
- Name the Idaho national forests and say who signs plan and project decisions at the forest level
- Explain what a forest plan does and does not decide, and how a project must fit the plan
- Describe the Idaho Roadless Rule, the 2026 proposal to rescind the national Roadless Rule, and why the two are separate
- Use the Schedule of Proposed Actions and project pages to find a project, and tell which comment and objection steps apply
- Report what is confirmed, and what is still in motion, about the 2026 Forest Service restructure and the October court stay
Start here: the short version
- Idaho's national forests cover 20,451,561 acres, about 38.6 percent of the state, by the Congressional Research Service's September 2024 count. Each forest has a plan written under the National Forest Management Act. The plan sets the rules. Projects (a thinning, a trail, a timber sale, a grazing change) are decided one at a time by a forest supervisor or district ranger, and each must fit the plan.
- Public comment and objection are tied together. Under the Forest Service's pre-decisional objection rule, only people who submitted timely, specific written comments can object. A final rule published in the Federal Register on October 13, 2026 (91 FR 64760) and effective November 12, 2026 shortens the clocks to 10 days (EA) and 20 days (EIS) for objections, down from 45 days under the earlier rule.
- Since April 2026 the Forest Service has been under a department-wide NEPA rule (7 CFR part 1b) that makes public comment on most environmental assessments and categorical exclusions optional, at the responsible official's discretion.
- The restructure announced March 31, 2026 would close the nine regional offices (Missoula and Ogden among them), create a Boise state office for Idaho, and move headquarters to Salt Lake City. A federal judge stayed office closures and out-of-area relocations in October 2026. The stay is tied to appropriations language that runs to December 11, 2026.
- Facts here are from statutes, regulations, the Federal Register, the court order and agency pages, as of October 20, 2026. Several items are moving, and each is marked.
A national forest in Idaho is run by a short chain of people with names, titles and signatures. A forest supervisor signs the plan. A district ranger or the supervisor signs most project decisions. Above them sits an office that, as of this lesson, is being redrawn. A reader who knows who signs what, and which clock applies, can tell in any story whether a decision is final, still open to comment, or already past the point where a person can object.
Idaho's national forests and the people who run them
The Forest Service manages 20,451,561 acres in Idaho, according to the Congressional Research Service's Federal Land Ownership: Overview and Data (acreage as of September 30, 2024). Idaho covers 52,933,120 acres, so the arithmetic is 20,451,561 divided by 52,933,120, which is 0.386, or 38.6 percent. The Bureau of Land Management holds another 11,768,027 acres, or 22.2 percent, and the report puts the federal share of Idaho at 61.9 percent. Lesson 1 of this course covers the whole ownership map. This lesson stays on the national forests.
The Forest Service's own Land Areas Report, Table 28 (refreshed October 2023) lists the units that cover Idaho. The numbers below are each unit's total National Forest System acres, and several units cross state lines, so they do not add up to Idaho's 20.45 million.
| Unit (Forest Service code) | Region as of the 2023 table | National Forest System acres |
|---|---|---|
| Idaho Panhandle National Forests (0104) | Northern (Region 1) | 2,497,661 |
| Kootenai National Forest (0114; extends into Montana) | Northern (Region 1) | 2,243,172 |
| Nez Perce-Clearwater National Forests (0117) | Northern (Region 1) | 3,935,563 |
| Boise National Forest (0402) | Intermountain (Region 4) | 2,204,669 |
| Caribou-Targhee National Forest (0415; extends into Wyoming) | Intermountain (Region 4) | 2,900,157 |
| Payette National Forest (0412) | Intermountain (Region 4) | 2,310,301 |
| Salmon-Challis National Forest (0413) | Intermountain (Region 4) | 4,355,552 |
| Sawtooth National Forest (0414) | Intermountain (Region 4) | 2,111,977 |
Add the eight rows: 2,497,661 + 2,243,172 + 3,935,563 + 2,204,669 + 2,900,157 + 2,310,301 + 4,355,552 + 2,111,977 = 22,559,052. That is about 2.1 million acres more than the Forest Service's Idaho total, because Kootenai and Caribou-Targhee reach into other states and a few forests headquartered elsewhere (the Bitterroot, Bridger-Teton and Wallowa-Whitman, which manages Hells Canyon National Recreation Area) have small Idaho pieces that are not in this table. When a news story says "the Sawtooth has 2.1 million acres," that is the unit's total. It is not an Idaho-only figure for every forest.
The Nez Perce and Clearwater forests appear as one unit in the table, Nez Perce-Clearwater, which is how the Forest Service lists them. Older plans and maps may still say Nez Perce or Clearwater separately.
Who signs
Section 219.2 of the planning rule sets three levels of planning: national strategic planning led by the Chief, planning for each national forest or comparable unit, and project and activity planning. It says the supervisor of the national forest is the responsible official for developing and approving plans, amendments and revisions, unless a regional forester, the Chief, the Under Secretary or the Secretary acts instead. It says the supervisor or district ranger is the responsible official for project and activity decisions. The final objection rule (91 FR 64760) changes the project-level review: it eliminates the separate reviewing officer, so the responsible official reviews objections, and when that official is a district ranger or forest supervisor an official above the forest or grassland supervisor must concur before the response is finalized and posted. For an extraordinarily complex or high-volume EIS objection the official one level above the responsible official may add up to 15 days to the response. Plan-level objections under 36 CFR 219.56 still go to a reviewing officer.
Until the restructure takes hold, the officials above the forest supervisor (and the reviewing officers for plan objections and for the older project objections) have been the regional foresters, in Missoula for the Panhandle, Kootenai and Nez Perce-Clearwater and in Ogden for the southern forests, according to the Idaho Capital Sun's April 2026 report and a Boise National Forest objection notice naming the Intermountain Regional Forester's objection reviewing officer in Ogden. Who fills the concurrence role after the regional offices close is one of the open questions later in this lesson.
How to: find out who signs a decision on your forest
- Open the forest's project page and look for the "responsible official" line in the notice. On a Forest Service comment page it appears near the top, with a contact for the project team.
- Check whether the decision is a plan decision (the supervisor signs) or a project decision (the supervisor or a district ranger signs). The notice will say which.
- For an objection, find the filing instructions in the notice. Under the earlier rule the notice named a reviewing officer (for the Clear Creek notice, the Intermountain Regional Forester's reviewing officer in Ogden). Under the final rule effective November 12, 2026 the responsible official reviews the objection and an official above the supervisor concurs. Do not assume the office is the same as last year, because of the restructure.
- Call the district office. The ranger district phone numbers are on each forest's web page, and staff can say which official has the decision.
Forest plans: what they decide and what they leave open
The National Forest Management Act, 16 U.S.C. 1604, tells the Secretary of Agriculture to develop, maintain and, as appropriate, revise land and resource management plans for each unit, coordinated with state, local and other federal planning. Plans must provide for multiple use and sustained yield under the Multiple-Use Sustained-Yield Act of 1960, which names outdoor recreation, range, timber, watershed, and wildlife and fish, and they must coordinate wilderness with those uses. Plans are revised when conditions have significantly changed and at least every 15 years. Subsection (i) says permits, contracts and other instruments for using national forest land must be consistent with the plan.
The statute as printed by Cornell carries a note from 2026 appropriations law: the Secretary is not in violation of the 15-year requirement solely because the time has passed, if the Secretary is acting expeditiously and in good faith. That matters in Idaho, where several plans date from the 1980s and are in the long process of revision. The Salmon-Challis National Forest, for example, describes its project as revising "the 1987 Challis and the 1988 Salmon" plans. The Idaho Panhandle National Forests operate under a plan adopted January 5, 2015, which replaced a 1987 plan. The stage of revision of every Idaho forest could not be confirmed from a current Forest Service page, so check each forest's planning page before relying on a date.
What is in a plan
Section 219.7(e) lists the required plan components. They are the vocabulary of every forest plan story.
| Plan component | What it is | Why it matters to a reader |
|---|---|---|
| Desired conditions | Descriptions of the conditions the Forest Service wants the land to reach | Sets the target a project is measured against |
| Objectives | Measurable, time-specific steps toward desired conditions | The numbers an agency can be held to, such as acres treated |
| Standards | Mandatory constraints on project and activity decisions | A project that breaks a standard needs a plan amendment |
| Guidelines | Constraints that allow departure if the purpose is met | A project may depart if it explains why the purpose is still served |
| Suitability of lands | Which lands are suitable for uses, including which are unsuitable for timber production | Where timber production is allowed at all |
| Management areas | Geographic areas with their own direction | Tells you which rules apply to your drainage |
The planning rule says a plan provides a framework for integrated resource management and guides project decisions. It does not authorize projects or commit the Forest Service to take action. That sentence is the most useful one in the rule for reading headlines. A forest plan that lists a hundred thousand acres as "suitable" for timber has not approved a single sale. Each sale still needs its own environmental review and decision.
Timber and the plan
Section 219.11 requires plans to identify lands unsuitable for timber production for reasons such as a legal bar, a withdrawal, a conflict with plan goals, soil or watershed damage the current technology would cause, or the inability to restock within five years. The designations are reviewed every 10 years. The rule also caps the amount of timber sold at what the forest can sustain indefinitely, which can be measured over a decade, and a departure from that limit requires at least 90 days of public comment. The rule also allows cutting on lands not suited for production for other purposes, such as reducing fire risk or improving wildlife habitat, and allows salvage and sanitation cuts. Reading a plan for timber means reading two things: the lands suitable for production, and the separate allowance for harvest done for other purposes.
How to: read a forest plan for one place
- Find the forest's plan page and download the current plan and its final environmental impact statement. If the forest is in revision, download the assessment and the draft too.
- Find the management area map. Locate your drainage, trailhead or allotment and note the management area name.
- Read that management area's desired conditions, standards and guidelines. Standards are the binding lines.
- Check the suitability tables for timber, and the sections on wilderness recommendations, wild and scenic river eligibility and inventoried roadless areas.
- Check the plan's monitoring section and the latest monitoring report. The planning rule says monitoring reports are issued every two years and feed back into the plan.
- Write down the plan's date and any amendments. A project proposed today is judged against the plan as amended today.
How a plan gets revised, and where the public comes in
A revision starts with an assessment of existing information, then a finding of whether the plan needs to change, a proposed plan with an environmental impact statement, public comment (at least 90 days on a plan or revision with a draft EIS, under 36 CFR 219.16), an objection period, and approval. Objection to a plan under section 219.56 must be filed within 60 days of the public notice when an EIS is involved, or 45 days for an amendment without one, with no extensions except when a deadline falls on a weekend or federal holiday. The reviewing officer must respond in writing within 90 days after the filing period ends and may extend that period. Plan objections follow the older plan-level rules in part 219. The project-level rules in part 218 are the ones the new final rule changes.
Plans are the place to weigh in on big-picture questions: which lands are recommended for wilderness, what a forest's role is for timber, how much of a drainage is open to motor vehicles, how big a buffer a stream gets. Once a plan is approved, those choices become the frame for years of projects. Commenting early on the plan is usually more effective than arguing about a single project that already fits it.
Special places: wilderness, roadless areas and travel
Congress, not the Forest Service, designates wilderness. The largest in Idaho is the Frank Church-River of No Return Wilderness, created by Public Law 96-312 in 1980 and renamed in 1984, with 2,239,000 acres, according to Wilderness.net, which also notes it spans six national forests and includes a small piece managed by the BLM. A plan can recommend more wilderness, but only Congress can create it. The same is true of wild and scenic rivers: the Forest Service studies eligibility in planning, and designation comes from Congress or the Secretary under that Act's procedures.
Two roadless rules, not one
The 2001 Roadless Area Conservation Rule (36 CFR part 294, subpart B) is the national rule that prohibits road construction, road reconstruction and timber harvest in inventoried roadless areas, with exceptions. It covered about 58.5 million acres nationwide, according to the proposal discussed below. Idaho has its own rule, the Idaho Roadless Rule, at 36 CFR part 294, subpart C. Its text places Idaho roadless lands in five management classifications: Wild Land Recreation, Special Areas of Historic or Tribal Significance, Primitive, Backcountry/Restoration, and General Forest, Rangeland and Grassland. Section 294.24 sets timber rules by classification. Cell by cell:
| Classification | Timber cutting, sale or removal (36 CFR 294.24) |
|---|---|
| Wild Land Recreation | Prohibited, with exceptions for personal or administrative use and activities incidental to other permitted management |
| Special Areas of Historic or Tribal Significance, and Primitive | Prohibited except for listed purposes: habitat for threatened, endangered, proposed or sensitive species; restoring natural characteristics of the area; reducing the risk of uncharacteristic wildfire to at-risk communities or municipal water supplies; personal or administrative use; incidental activities. Projects must maintain or improve roadless characteristics, and the Regional Forester approves them |
| Backcountry/Restoration | Allowed for more purposes, including hazardous fuels reduction in the community protection zone and, where fire risk to a community or water supply is significant, outside it. Most actions need Regional Forester approval |
| General Forest, Rangeland and Grassland | Timber may be cut, sold or removed if consistent with the forest plan |
Section 294.25 adds limits for mineral leases: no road construction or reconstruction, or surface occupancy tied to leases, in the three most protected classifications, no road building in Backcountry/Restoration, and a general bar in the General Forest classification with an exception for phosphate deposits shown in the rule's Figure 3-20. The rule took effect October 16, 2008, a date the text itself uses as a reference point. It grew out of a petition from the State of Idaho; the Governor's October 5, 2006 petition covered about 9.3 million acres of inventoried roadless areas in Idaho, which that document describes as the largest acreage in the contiguous United States (and 275 areas). Using the same document's figure of about 20.5 million acres of Idaho national forest, 9.3 divided by 20.5 is 0.45, so about 45 percent of Idaho's national forest acreage was in the roadless inventory at the time.
On August 20, 2026 the Forest Service published a proposed rule to rescind the 2001 national rule by removing and reserving subpart B. The notice says the Idaho (subpart C) and Colorado (subpart D) rules "will not be affected by this proposed rule and will remain in effect." If the proposal were finalized, management of roadless areas outside those two states would fall to each forest's plan. The notice says it does not authorize specific projects, any future timber or road proposal would still need site-specific NEPA review and be consistent with the plan, and local Forest Service officials would decide. A September 11 notice extended the comment deadline by 15 days, to October 6, 2026. That deadline has passed, so the next step is a final rule or further notice. Idaho's roadless lands matter to the story mainly as a contrast: the state's rule was written for Idaho and stays unless a separate rulemaking changes it.
The proposal's supporters, including the agency in the notice, argue that roadless decisions belong in forest planning where local conditions are considered. Opponents argue that a national prohibition protects areas that local plans could later open. Both positions are in the docket. A reporter should read the draft environmental impact statement that came with the proposal for the acreage and the agency's estimates of effects, and read the comments.
Travel management
Where motor vehicles may go is decided by designation. Under 36 CFR 212.55, the responsible official considers effects on natural and cultural resources, public safety, recreation, access needs and conflicts among uses, and minimizes effects on soil, watershed, vegetation and wildlife. Motor vehicle use maps show the designated routes. The Forest Service's September 2026 Policy Report describes an August 24, 2026 notice of intent to start an environmental impact statement and rulemaking to revise the travel management regulations at 36 CFR part 212, with a proposal to presume that existing roads, trails and routes are open to public use unless closure is justified. That description comes from the agency's own summary, so the Federal Register notice is the document to check.
Projects: where plans turn into decisions
A project is a specific proposal on specific ground: a thinning, a prescribed burn, a timber sale, a trail relocation, a mine plan of operations, a road decommissioning. The Forest Service lists projects on each forest's project page and in the Schedule of Proposed Actions. The Salmon-Challis SOPA is a good example of the format: projects grouped by forestwide scope and then by ranger district, with columns for project name and NEPA type (CE, EA or EIS), purpose, planning status, expected decision, expected implementation and a named contact. The same page listed the Salmon-Challis Forest Plan Revision EIS as "Developing Proposal," with an expected decision date in 2026, in an edition from early 2025. Treat any SOPA date as a forecast.
How to: find and follow a Forest Service project
- Start at the SOPA for the forest. Look for the project name, the NEPA level and the "planning status" column.
- Open the project page and look for the proposal, the maps and any comment link. Forest Service comment pages carry a project number, a responsible official and contact information.
- Note the date of every designated comment opportunity: scoping, a comment on an environmental assessment, or a comment on a draft EIS. Only these preserve your right to object.
- Watch for the legal notice. For projects under the objection process, the Forest Service says the legal notice published in the newspaper of record starts the clock, and a Boise National Forest notice for the Clear Creek Forest Health Project told readers not to rely on other sources for timing.
- When a decision notice appears, read the findings, the responsible official's name and the date. Implementation can begin after the objection period and any required response.
Which process applies to which project
| Project type | Usual NEPA level | Public comment | Objection |
|---|---|---|---|
| Small vegetation, trail or facility work that fits a categorical exclusion | CE with documentation or a record of applicability | At the responsible official's discretion under 7 CFR 1b | Not covered by the final Part 218 rule (EA and EIS projects are) |
| Larger thinning, fuels or restoration project | Environmental assessment and draft finding of no significant impact | Designated comment period of 15 days under the final Part 218 rule, where objection applies | 10 days after the draft FONSI is published |
| Large timber, mining or infrastructure project | Environmental impact statement and draft record of decision | Notice of intent comment; designated comment of 30 days under the final Part 218 rule, where objection applies | 20 days after the draft ROD is published |
| Emergency action under the April 2025 determination | Procedures cited by the Forest Service for emergency actions | Formal periods "won't typically be part," per a memo reported by E&E News | Emergency determinations do not apply to authorized Healthy Forests Restoration Act fuel reduction projects, per the final rule |
| Forest plan revision or amendment | EIS for plans and revisions; amendments depend on scope | At least 90 days on a plan or revision with a draft EIS (36 CFR 219.16) | 60 days (45 days for an amendment without an EIS) |
Read the table as a map, not a guarantee. The emergency row rests on a reported memo and the final rule's coverage section, and the other rows rest on rules that took effect or are scheduled to take effect in 2026. The Forest Service's own project notice controls for any given project.
Common mix-ups
- Claim: "The forest plan approved this timber sale." What the evidence shows: The planning rule says a plan does not authorize projects or commit the Forest Service to action. A sale still needs its own NEPA review and a decision signed by a supervisor or district ranger.
- Claim: "The national Roadless Rule repeal ends Idaho's roadless protections." What the evidence shows: The August 2026 proposal would remove the 2001 national rule only. The Federal Register text says the Idaho Roadless Rule remains in effect.
- Claim: "If I did not comment, I can still object." What the evidence shows: Under the final Part 218 rule, only people and entities who submitted timely, specific written comments during a designated opportunity can object (Tribes also may through consultation). Federal agencies may not object.
- Claim: "Each forest's acres are Idaho acres." What the evidence shows: Several units cross state lines. The eight units in the Forest Service's table add to about 22.6 million acres, while Idaho's national forest total is 20.45 million.
NEPA in 2026: the rules the Forest Service now follows
On April 3, 2026 USDA published a department-wide rule at 7 CFR part 1b that replaced most agency-specific NEPA regulations. A law firm's summary (WilmerHale, April 27, 2026) reports the main changes: categorical exclusions are centralized at the department level, 48 require documentation and 39 do not, public comment is generally limited to statutory requirements, the notice of intent for an EIS is the only required comment point, and comment on environmental assessments, categorical exclusions and draft EISs is now at the responsible official's discretion. Officials must consider substantive comments and "should address in writing" them but "need not address every comment individually." The same summary says the Forest Service's administrative review rules in 36 CFR parts 218 and 219 stay in effect. Lesson 7 covers NEPA in detail.
The Forest Service then finalized part 218. According to the final rule, published October 13, 2026 at 91 FR 64760 (document 2026-20890, RIN 0596-AD69) and effective November 12, 2026, the numbers are:
| Item | Earlier figure, where the sources state one | Final rule |
|---|---|---|
| Comment period, EA-level project | 30 days | 15 days, no extension |
| Comment period, EIS-level project | 45 days | 30 days, no extension |
| Objection filing period, EA and draft FONSI | 45 days after the legal notice under 36 CFR 218.26 (the Clear Creek notice on the Boise National Forest gave 30 days, the period used for Healthy Forests Restoration Act projects) | 10 days after the draft FONSI is published on a USDA website |
| Objection filing period, EIS and draft ROD | 45 days after the legal notice of the final EIS under 36 CFR 218.26 | 20 days after the draft ROD is published |
| Response to objection, EA | 45 days, per the February 2026 proposal's description of the old rule | 15 calendar days |
| Response to objection, EIS | 45 days, extendable by 30, per the same proposal | 20 calendar days, extendable by 15 for a total of 35 |
| Objection page limit | No figure in the sources read | 15 pages (EA), 30 pages (EIS), attachments excluded |
| Response length | No figure in the sources read | No more than five pages, posted on a USDA website |
Other points from the final rule: the filing period cannot be extended; publication of the draft decision document on a USDA website (replacing the newspaper legal notice) is the trigger; the separate reviewing officer is eliminated and the responsible official reviews objections; a district ranger or forest supervisor decision needs concurrence from an official above the forest or grassland supervisor before the response is posted; the guaranteed objection-resolution meeting is removed, though officials may still hold meetings; a final FONSI or ROD may be published only after the fifth business day following the end of the objection period; Healthy Forests Restoration Act projects fall under the same standardized process; categorical exclusions are not subject to objection; the proposed rule's comment periods were 10 days (EA) and 20 days (EIS) and the final rule lengthened them to 15 and 30; mitigation citations are encouraged, not required; and the Forest Service says the change cuts review time, citing 120 to 150 days of added time in the existing EA process and 135 to 165 days in the EIS process. About 2,270 comments were received on the proposal. The rule has a transition framework that generally keeps the prior rule for projects whose legal notices were published before the proposed rule appeared on February 6, 2026 (91 FR 5387), with added conditions for later notices, so check the project's own notice before telling anyone which clock applies to a live project.
A worked example on the clock
An invented project: the Alder Fork thinning on the invented Pinecrest Ranger District. The district posts a draft FONSI and draft decision for an environmental assessment on June 1 of a year after the final rule takes effect (the final rule took effect November 12, 2026). The objection period is 10 days, so it closes June 11, a day that is not a weekend or federal holiday in this example. A resident who sent specific written comments in the 15-day EA comment period can object. A resident who only sent a one-line message to a ranger in April, outside a designated comment opportunity, cannot. The response period starts the day after the objection period closes, June 12, and runs 15 calendar days, to about June 26. The final FONSI can be published only after the fifth business day after the objection period ends. Under the earlier 45-day clock a resident would have had until about July 16. The calendar changes who can act. Anyone who wants to preserve a right to object has to comment early, specifically and in writing.
How to: preserve your right to object
- Identify the designated comment opportunity: scoping, an EA comment period or a draft EIS comment period. Look for those words on the project page.
- Write your own comment. Include your name and contact information, the project name and forest, specific issues with reasons, and a recommended remedy. Members of an organization must file their own comments if they want to object personally.
- Submit by the stated method before the deadline. Hard-copy comments count under the final rule if the postmark (or private carrier shipping date) is on or before the deadline and the item is received before the close of the fifth business day after the period ends. Electronic submissions are timely by the system's date and time, and comments on external media such as CDs or drives are not accepted.
- If you object, link each issue to your earlier comment, or to the exception for new information that arose after the comment period.
- Keep a copy of every submission and its confirmation.
Timber, emergency authority and Good Neighbor Authority
Three policy levers drive timber and fuels work on Idaho's national forests in 2026.
- The 2025 emergency determination. On April 3, 2025 Agriculture Secretary Brooke Rollins issued a secretarial memo (SM 1078-006) establishing an Emergency Situation Determination covering 112,646,000 acres of National Forest System land, tied to an executive order to expand American timber production by 25 percent, according to USDA's April 4, 2025 release. The release says it lets the Forest Service expedite work on the ground and carry out authorized emergency actions to reduce wildfire risk. E&E News reported that an implementation memo said formal public comment periods "won't typically be part of projects" under the determination.
- The new NEPA rule. Under 7 CFR part 1b, comment on most EAs and categorical exclusions is at the responsible official's discretion, as above.
- Good Neighbor Authority. 16 U.S.C. 2113a lets the Secretary of Agriculture (and Interior for BLM land) enter a good neighbor agreement with a governor or county for forest, rangeland and watershed restoration services on federal, non-federal and tribal land. Revenue from timber sold under an agreement is kept by the governor, tribe or county for authorized restoration services, and that revenue authority ends October 1, 2028. Restoration services exclude building or rebuilding paved or permanent roads. The statute says NEPA decisions for these services on federal land cannot be delegated to a governor or county.
Idaho's use of the authority is on paper in the 2025 Agreement for Shared Stewardship between the State of Idaho and the Forest Service's Northern and Intermountain Regions. It says Idaho has about 21.5 million acres of forestland, including 16.5 million acres of productive timberland, and more than 6.4 million forested acres at high or very high risk of wildfire, insects or both. It reports 64 GNA sales over more than 16,500 acres of federal forestland in the last decade, more than 209 million board feet and more than $21 million in receipts, with Forest Service investment of $17.8 million, $2.2 million in state funds and $1.2 million in forest-industry funds. GNA sales made up 18 to 27 percent of annual volume sold from partnering national forests from 2016 to 2024. The agreement sets a target of up to 100 million board feet a year through GNA within five years, which it describes as double current output, and says IDL has GNA agreements with seven national forests. The agreement is nonbinding and creates no enforceable rights. It also says the then-current IDL GNA agreement expires in May 2026 and a new statewide agreement was to be developed.
A worked example on board feet and acres
An invented project: the Alder Fork thinning treats 2,000 acres of the invented Pinecrest district, of which 750 acres are commercial at an average 9,000 board feet an acre. Volume: 750 times 9,000 is 6,750,000 board feet, or 6.75 million. Against the 100-million-board-foot GNA target, the project is 6.75 divided by 100, or 6.75 percent of one year's goal. Acres and board feet are different measures. A story that says "2,000 acres of logging" overstates the commercial piece, because only 750 acres in this example produce sawlogs. A story that says "6.75 million board feet" without acres hides how much ground is treated. Report both, and say which acres are commercial.
The Sawtooth examples
Several 2026 reports describe a Sawtooth National Forest thinning project north of Ketchum, and their details differ. The Idaho Capital Sun's April 15, 2026 story reported that in December a Sawtooth National Forest project of about 2,500 acres was proposed, that under previous rules it would have had two 30-day comment periods, and that it was proceeding under emergency authorization with no official comment period, with an informational open house on May 11. The Idaho Conservation League's explainer (May 2026) also gives about 2,500 acres along Highway 75 between Baker Creek and Galena in the Sawtooth National Recreation Area, but says the project is proposed under a categorical exclusion with no formal comment period, and it does not mention an emergency determination. The Mountain Express reported on the Upper Big Wood (Upper Bigwood) vegetation project, about 2,800 acres roughly 20 miles north of Ketchum around Prairie Creek, Cherry Creek, Senate Creek and Galena Lodge. It reported that the deciding official, Michael Fuller, acting area ranger for the Sawtooth National Recreation Area, found in March that no formal comment period was needed, that a categorical exclusion was expected, and that the decision slipped from late June or July to September so the agency could confirm Endangered Species Act compliance. It also reported that the Blaine County commissioners wrote the Forest Service urging it to reconsider skipping public comment, and that the Idaho Conservation League asked the agency to press pause. A May 11 open house appears in both the Capital Sun and Mountain Express accounts, which points to one project, but no Forest Service decision document confirming the acreage or the legal authority could be retrieved. The agency's project page (project 172623, "Upper Big Wood Vegetation Management," last updated September 18, 2026) has headings for an overview and documents but no acreage, NEPA type or decision text in the version read. Acreage is reported as about 2,500 or about 2,800, and the legal route is reported as emergency authorization (Capital Sun) or categorical exclusion (Mountain Express and the Conservation League). A reporter should ask the Sawtooth supervisor's office for the project number, the acreage and the authority actually used in the decision document, and should not treat the emergency determination and the categorical exclusion as the same thing.
The 2026 restructure, step by step
The most recent official summary is the Forest Service's reorganization page, last modified October 15, 2026. A timeline built from the agency page, press reports and the court order is below.
| Date | What happened | Source |
|---|---|---|
| July 2025 | USDA announced a department-wide reorganization (Secretary's Memorandum 1078-015) | Forest Service timeline (as read earlier; confirm on the agency page) |
| March 31, 2026 | Forest Service announced headquarters would move from Washington to Salt Lake City and the agency would adopt a state-based model with 15 state directors, replacing nine regions | Forest Service and press reports |
| April 15, 2026 | Idaho Capital Sun reported Idaho would get a single state office in Boise, replacing the Ogden and Missoula regional offices; agency said the 15 state director jobs would be filled exclusively by career federal employees; about 500 employees expected to relocate | Idaho Capital Sun |
| August 24 and 31, 2026 | Senior leadership assignments announced, including five State Directors | Forest Service timeline (as read earlier; not visible on the October 15 version of the page, so confirm) |
| September 3, 2026 | Facilities review completed: 23 facilities to close, more than $16 million in savings claimed (the agency page gives the 23 closures and the $16 million, and the September 3 date comes from the earlier timeline) | Forest Service |
| October 13 to 14, 2026 | Federal court in the Northern District of California issued a stay order in Case No. 26-cv-09976-VC on closures and relocations | Order and Forest Service page |
| December 11, 2026 | Date the appropriations restrictions the order relies on are set to expire under a continuing resolution, unless Congress extends them | Order and Deseret News |
What the restructure changes for Idaho
According to the agency page, Idaho will have a state office in Boise among 15 state offices, six operations service centers in Placerville, Fort Collins, Athens, Missoula, Albuquerque and Madison, a research unit consolidated in Fort Collins, and headquarters in Salt Lake City. The agency says wildfire operations stay largely as they are, reporting to the deputy chief for fire and aviation management at the National Interagency Fire Center in Boise, per Federal News Network. The page says the agency has about 30,000 employees, that fewer than 200 are expected to relocate, mostly from the Washington, D.C. office, and that "There is a job for every existing employee in the reorganization." That differs from the April report of about 500 relocations. The page ties the footprint reduction to about $37 million less in facilities funding in fiscal 2026 than in 2025 and a $3 billion deferred maintenance backlog, and says the full model is expected to be implemented "later this fall," after fire activity subsides.
The planning rule's text, as read in October 2026, still names the forest supervisor and district ranger as the responsible officials for plans and projects. The restructure as described moves the layer above them. What it does to reviewing officers, to species-of-conservation-concern lists that the planning rule assigns to regional foresters, to staffing in the Boise office and to wait times for approvals has not been published in detail in the sources read for this lesson. Those are the questions to ask.
The October stay
The order, filed October 13, 2026 in the U.S. District Court for the Northern District of California, grants a stay under 5 U.S.C. 705 postponing USDA closures of offices and relocations or reassignments of employees outside local commuting areas at the Forest Service and a list of other USDA components (the Agricultural Research Service, Foreign Agricultural Service, Rural Development, the Office of the General Counsel and others), including "management directed reassignment" letters and their deadlines, while the case proceeds (American Federation of Government Employees v. USDA, Dkt. 107). The plaintiffs are federal-worker unions (the American Federation of Government Employees, AFSCME, the National Federation of Federal Employees and the National Treasury Employees Union), joined by local governments and nonprofits. The defendants are USDA and Secretary Rollins. The court found the plaintiffs likely to succeed in showing the closures and relocations are not in accordance with law, relying on reprogramming restrictions in appropriations acts (Pub. L. 119-37 and 119-74), and severed committee-approval clauses that both sides agreed were unconstitutional. The Deseret News identified the judge as Vince Chhabria and described the ruling as a bar on spending appropriated funds on the challenged closures and relocations through at least December 11; the order itself says Congress "recently extended them until December 11, 2026" by a continuing resolution (Pub. L. 119-103), so Congress can extend or let lapse the restrictions. The order excepts moves within the National Capital Region and certain employee-initiated reassignments. Utah's governor, Senate president and House speaker criticized the ruling and hoped it would be quickly reversed. The Forest Service's page lists the Administrative Stay Order on October 14. On October 23, 2026, Agriculture Secretary Brooke Rollins said the department would press ahead with the reorganization, and the stay is under appeal, according to the Associated Press via Federal News Network.
What this means for an Idaho reader on October 20, 2026: the plan to close the regional offices and relocate staff is on hold by court order, at least until the appropriations restrictions expire on December 11, unless Congress extends them or the order changes. The state-office model announced in March has not been withdrawn. Anyone telling you the Boise office is open for business, or that Missoula and Ogden are closed, is ahead of the record.
Reporting angle
- Ask the forest supervisor's office for the current project list, the NEPA type and the responsible official for any project in your area. Ask who is the reviewing officer for objections now and who it will be after the restructure.
- For the restructure, request the organizational charts, position descriptions and vacancy counts for the Idaho forests and the Boise state office, and the staffing level before and after. Use the federal Freedom of Information Act through the Forest Service FOIA office. Lesson 10 covers the process, and the Idaho public records course covers the state side.
- Check which clock applies to a live project under the final Part 218 rule (91 FR 64760, published October 13, effective November 12, 2026, with a transition framework for older notices), and the status of the roadless proposal after the October 6 comment deadline.
- Read the court docket in Case No. 26-cv-09976-VC for the next hearing and any appeal.
- Numbers to check: acres versus board feet, the unit versus the Idaho portion of a forest, comment periods in calendar days, and whether a story's "emergency" project is an actual emergency action or a categorical exclusion.
- For local government: ask your county commissioners whether the county has asked for cooperating agency status or a Good Neighbor agreement, and see local government and planning and zoning for the county side.
Go further
- 16 U.S.C. 1604 and 36 CFR 219.7: the plan statute and the plan content rule.
- 7 CFR part 1b: USDA's NEPA procedures.
- Final Part 218 rule and the Roadless proposal.
- Forest Service reorganization page and the stay order.
- Lesson 8 on comments, objections and protests; lesson 7 on NEPA; lesson 1 on who owns Idaho.
- Testifying and public comment and laws and rules.
Questions and answers
How many national forests does Idaho have?
The Forest Service's land table lists eight units that cover Idaho: Idaho Panhandle, Kootenai, Nez Perce-Clearwater, Boise, Caribou-Targhee, Payette, Salmon-Challis and Sawtooth. Pieces of other forests headquartered in neighboring states also reach into Idaho. Counting depends on whether you count units or forests, so name the units when you write.
Who decides whether a forest plan is revised?
NFMA requires revision when conditions have significantly changed and at least every 15 years, but a 2026 appropriations note says the Secretary is not in violation solely because the time has passed if the Secretary is acting expeditiously and in good faith. The forest supervisor approves a revision unless a higher official acts.
Does a forest plan approve a timber sale or a trail?
No. The planning rule says a plan guides project decisions and does not authorize projects or commit the Forest Service to action. A project must fit the plan, but a project decision must still be made.
What is the Schedule of Proposed Actions?
It is a Forest Service list, by forest, of planned and ongoing projects with the NEPA type, planning status, expected decision and implementation dates and a contact. Dates are forecasts, and the Salmon-Challis list in the 2025 edition showed the plan revision decision expected in 2026.
Do I have to comment to object?
Yes. Under 36 CFR 218.6 in the final rule, only individuals and entities that submitted timely, specific written comments during a designated opportunity may object, with a Tribal consultation exception. Under 36 CFR 219.53, plan objections likewise require substantive formal comments during the comment opportunity.
What is the difference between a comment and an objection?
A comment is your input during the analysis. An objection is a pre-decisional review step after a draft decision exists, in which an official looks at the issues you raised earlier. For plans, a reviewing officer responds under 36 CFR 219.56. For projects under the final Part 218 rule, effective November 12, 2026, the responsible official responds with concurrence from an official above the forest or grassland supervisor, and responses are posted online.
Does the Idaho Roadless Rule go away if the national Roadless Rule is rescinded?
The August 2026 proposal says the Idaho and Colorado rules remain in effect. Only a separate rulemaking would change the Idaho rule.
Can Idaho or a county take over a federal timber sale?
Not the NEPA decision. Good Neighbor Authority lets a state or county do the work under an agreement and keep the sale revenue for restoration, but the statute says NEPA decisions on federal land cannot be delegated.
Is the Boise state office open?
The agency page lists an Idaho State Office in Boise. A court stay now blocks office closures and out-of-area relocations while the case proceeds, so the regional offices stay open while the stay is in force. The agency said the full model would roll out in phases after fire season.
Hard questions
"Is it right to make public comment optional?"
USDA's April 2026 rule limits required comment to the notice of intent for an EIS and leaves other comment to the responsible official. Supporters say it speeds projects, and the final Part 218 rule cites 120 to 150 days of added time in the existing EA process and 135 to 165 days in the EIS process. Opponents, including Blaine County commissioners in the Upper Big Wood case, say a project of that size deserves a formal comment period. Officials must still consider substantive comments they receive. The fact in dispute is whether shorter windows reduce delay without reducing the quality of the record. The record shows the windows are shorter. Whether the outcomes differ will take years of project decisions and court cases to show.
"Should the Forest Service be run from Salt Lake City and Boise, or from Washington?"
Agriculture Secretary Brooke Rollins and Chief Tom Schultz said the move puts the agency closer to the forests it manages. Idaho's members of Congress quoted in the April report called it an opportunity and a stronger focus on the West. A retiree association spokesman said you do not get more work done with fewer people, and an Idaho conservation group said the state-office model might help but questioned how services would be reallocated and said public forums were being eliminated. The April report also raised the 2019 BLM headquarters move as a precedent: of 311 positions scheduled to move west, 90 accepted reassignment, per a 2020 GAO report, and the move was reversed in 2021. The facts that would settle the question, including service levels and staff retention, are not yet in.
"Do emergency determinations help or hurt forest health?"
The April 2025 determination covers 112.6 million acres, and the USDA says it lets the agency act faster to reduce wildfire risk. Forest policy groups quoted by E&E News said the scope of the determination was "unprecedented, if not questionable," and noted that reducing public engagement is not unusual after a disaster. Idaho's Shared Stewardship Agreement counts more than 6.4 million forested acres at high or very high risk. Both sides cite the same risk. They differ on whether speed or process is the better tool.
"Should roadless decisions be national or local?"
The 2001 rule set a national floor, and Idaho's 2008 rule shows that a state-specific rule can fit local conditions, because it grew out of a petition from the Governor in 2006. The 2026 proposal returns the question to forest plans in other states. The tradeoff is consistency against local fit, and the final rule has not been issued.
"If the court stay lifts, what happens to staff?"
The order says it is tied to appropriations restrictions that expire December 11 unless extended. The order notes that Congress extended them to that date through a continuing resolution. Nothing in the sources read for this lesson says what the agency will do in that case beyond the phased plan the agency page describes. The honest answer is that the record does not say yet.
Check yourself
1. Under 36 CFR 219.2, who is the responsible official for developing and approving a forest plan, plan amendment or plan revision, unless a higher official acts instead?
Section 219.2 names the supervisor of the national forest, grassland or comparable unit as the responsible official for plans. The supervisor or district ranger is the responsible official for project and activity decisions.
2. What does the August 20, 2026 proposed rule say about the Idaho Roadless Rule (36 CFR part 294, subpart C)?
The proposal would remove and reserve subpart B. The Federal Register text says the Idaho and Colorado state-specific rules are not affected and remain in effect.
3. Under the Forest Service's final project-level objection rule (36 CFR part 218, published October 13, 2026 at 91 FR 64760 and effective November 12, 2026), how long is the objection filing period for an environmental assessment with a draft finding of no significant impact?
The final rule sets 10 days after the draft FONSI is published on a USDA website for EA-level projects, and 20 days after the draft record of decision for EIS-level projects. The period cannot be extended.
4. Who may file an objection to a Forest Service project under the final Part 218 rule?
Section 218.6 limits objections to those who submitted timely, specific written comments in a designated opportunity (with a Tribal consultation exception). Federal agencies may not object.
5. What did the October 2026 order in Case No. 26-cv-09976-VC (N.D. Cal.) do to the Forest Service restructure?
The order grants a stay under 5 U.S.C. 705 on closures and out-of-area relocations, relying on appropriations restrictions that expire December 11, 2026 under a continuing resolution unless Congress extends them.
6. Under the Good Neighbor Authority statute (16 U.S.C. 2113a), can a state or county take over the NEPA decision for work on national forest land?
The statute lets states, counties and tribes do restoration work under an agreement, but the federal NEPA decision stays with the federal agency.
Terms in this lesson
- Forest plan
- The land and resource management plan for a national forest. It sets desired conditions, objectives, standards, guidelines and suitable uses, but it does not by itself approve a project.
- Responsible official
- The Forest Service official who makes a decision: the supervisor for plans, the supervisor or district ranger for projects.
- Categorical exclusion (CE)
- A class of actions that USDA has found do not normally have significant environmental effects, so no environmental assessment or impact statement is prepared unless extraordinary circumstances apply.
- Objection
- The pre-decisional review step for Forest Service plans and projects. Only people who first submitted timely, specific written comments may file one.
- Inventoried roadless area
- A national forest area identified in the roadless inventory. In Idaho the state-specific Idaho Roadless Rule (36 CFR 294 subpart C) governs these lands.
- Federal law that lets the Forest Service and BLM sign agreements with states, counties and tribes to do forest, rangeland and watershed restoration work, including timber sales, on federal land.
- Schedule of Proposed Actions (SOPA)
- A quarterly Forest Service list, by forest, of projects that are planned or underway, with the NEPA type, status and a contact.
Sources
- Idaho Capital Sun, Forest Service restructure will see Idaho managed under new state office (Apr. 15, 2026) checked 2026-10
- USDA Forest Service, Forest Service Reorganization (agency page, updated Oct. 15, 2026) checked 2026-10
- U.S. District Court, N.D. Cal., Case No. 26-cv-09976-VC, stay order (Oct. 2026) checked 2026-10
- Deseret News, Federal judge blocks relocation of Forest Service headquarters to Utah (Oct. 15, 2026) checked 2026-10
- Federal News Network, Forest Service will move headquarters to Salt Lake City (Apr. 2026) checked 2026-10
- 16 U.S.C. 1604, National Forest System land and resource management plans checked 2026-10
- 36 CFR 219.2, Levels of planning and responsible officials checked 2026-10
- 36 CFR 219.7, New plan development or plan revision checked 2026-10
- 36 CFR 219.56, Filing an objection to a plan checked 2026-10
- 36 CFR 294.24, Timber cutting in Idaho Roadless Areas checked 2026-10
- Federal Register, Special Areas; Roadless Area Conservation, proposed rule (Aug. 20, 2026), FR Doc. 2026-16965 checked 2026-10
- Federal Register, Special Areas; Roadless Area Conservation, extension of comment period (Sept. 11, 2026), FR Doc. 2026-18648 checked 2026-10
- Federal Register, Project-Level Predecisional Administrative Review Process, final rule (36 CFR part 218), 91 FR 64760 (Oct. 13, 2026), effective Nov. 12, 2026, FR Doc. 2026-20890 checked 2026-10
- 36 CFR 218.26, Objection time periods (rule in effect before Nov. 12, 2026) checked 2026-10
- Idaho Conservation League, The Upper Bigwood Project: Here's What You Need to Know checked 2026-10
- Forest Service, Upper Big Wood Vegetation Management (Sawtooth National Forest project 172623) checked 2026-10
- eCFR, 7 CFR part 1b, USDA National Environmental Policy Act procedures checked 2026-10
- USDA, Secretary Rollins announces sweeping reforms to protect national forests and boost domestic timber (Apr. 4, 2025) checked 2026-10
- State of Idaho and USDA Forest Service, Agreement for Shared Stewardship (2025) checked 2026-10
- 16 U.S.C. 2113a, Good Neighbor Authority checked 2026-10
- Congressional Research Service, Federal Land Ownership: Overview and Data, R42346 (updated Sept. 14, 2026) checked 2026-10
- USDA Forest Service, Land Areas Report 2023, Table 28, NFS acres by administrative unit checked 2026-10
- Mountain Express, Big Wood vegetation management project decision delayed 2 months (2026) checked 2026-10
- Forest Service, Clear Creek Forest Health Project public notice (objection instructions, Boise National Forest) checked 2026-10
- Forest Service, Policy Report, September 2026 checked 2026-10
- Wilderness.net, Frank Church-River of No Return Wilderness checked 2026-10
- 36 CFR 212.55, Criteria for designation of roads, trails, and areas checked 2026-10
- WilmerHale, US Department of Agriculture Finalizes Updated NEPA Procedures (Apr. 27, 2026) checked 2026-10
- E&E News, Forest Service skirts public input on emergency logging plan (Apr. 2025) checked 2026-10
- Forest Service Salmon-Challis National Forest, Schedule of Proposed Actions (early 2025 edition) checked 2026-10